15 | Monitoring and Controlling Project Constraints Flashcards
In this lesson, you will: • Control the project scope. • Control the project schedule. • Control project costs. • Manage the project quality.
Verified Deliverables?
Verified deliverables are project products or results that are completed and verified for their
correctness after performing quality control. These deliverables are used as inputs during scope
validation of the project to determine if work is complete and satisfies project objectives
Inspections?
An inspection is an official examination of work results to verify that requirements are met. It is sometimes referred to as a review, product review, audit, or walkthrough. An inspection may be conducted by an internal or external inspection team.
During scope verification, an inspection
typically involves?
- Comparing baseline specifications and any approved changes to the actual project results.
- Determining the likelihood that remaining deliverables will be completed as promised.
• Identifying actions that may be needed to ensure that work results will meet the specifications, scope, or schedule and budget goals. In some cases, your team will be asked to conduct the inspection. In other cases, stakeholders may decide to ask an outside entity to either conduct the inspection or to participate with you in
conducting it.
What are the 4 inspection report components?
- Project baseline and status comparison:
The comparison of baseline specifications, schedules, and budgets to the actual project results for the project phase or deliverable. - Overall project status:
A discussion of whether the project as a whole is on track, or whether it is likely to deviate in some way from project plans. - Change recommendations:
Based on the inspection result, recommended changes that will be needed in order to meet the specifications, scope, or schedule and budget goals. - Scope and methodology of the inspection:
An explanation of what the audit attempted to prove, how it went about proving it, what measurements were used to determine conformance to requirements, and what assumptions or limitations influenced the way that data was collected.
Variance?
Variance is the quantifiable deviation from the expected results for any component of a product and service being developed, including scope, quality, schedule, and cost. Variance can be extreme or almost undetectable; it may result from many internal and external causes, such as problems with resource availability, or from the skills of personnel assigned to the project. Variance may be
obvious the moment a product is produced or may become obvious over time through use and exposure to environmental conditions. To control quality, you must recognize the difference between quality variance within a normal range and variance that indicates a quality error.
Variance Analysis?
Variance analysis is the comparison of the difference between the actual or predicted results and the original scope baseline or expected results. Any variances must be analyzed to determine whether they are acceptable or they merit corrective action to keep the performance within specifications. Scope control includes determining the cause and degree of variance relative to the scope baseline and deciding if any corrective or preventive action is necessary
Work Performance Measurements?
Work performance measurements involve calculating the variance between the planned and actual technical performance or other scope performance measurements. The results of performance measurements are documented, generally consolidated in the form of performance reports, and then communicated to project stakeholders. The report may include items such as:
- Features of the product planned versus features of the product being delivered.
- Any addition to or deletion from the features list.
- New changes to the project scope
Scheduling Tools?
Scheduling tools are tools that use updated schedule data combined with project management software or other methods to perform schedule network analysis and generate an updated project schedule. These tools accelerate the scheduling process by generating start and finish dates of activities based on their inputs, creating network diagrams, and producing resource and activity
duration.
EVM stands for?
Earned Value Management (EVM)
Earned Value Management (EVM)?
Earned Value Management (EVM) is a method of measuring project progress by comparing the actual schedule and cost performance against planned performance as laid out in the schedule and cost baselines. Assessing the value of work requires first determining what work has actually been performed and, therefore, what value it has contributed to the project.
During planning, project work is broken down into work packages and activities. Each work package is assigned a budget and schedule. Because each increment of work is time-phased, a Schedule Variance (SV) results when work is not completed as scheduled. It is always better to
understand the monetary value of work contribution as it relates to the schedule. Therefore, SV is often expressed in terms of the monetary value.
PV stands for?
Planned Value.
Planned Value (PV)?
Planned Value (PV) is the budgeted portion of the approved cost estimate to be spent during a particular time period to complete the scheduled project work. This amount is specified in the project’s cost baseline. In simpler terms, PV indicates the value of work to be done during a particular time period.
EV stands for?
Earned Value.
Earned Value (EV)?
Earned Value (EV) is a composite measurement of both cost and time performance in relation to scheduled or planned cost and time performance. EV is calculated by multiplying the percentage of work completed by the budgeted cost for the activity as laid out in the cost baseline.
In order to determine the EV of the project work to date, you will have to look back at the cost baseline to determine how costs were assigned originally. If the PV was determined by the percentage completed to date method, you will apply the same method of assessing the EV. In other words, EV indicates the value of work actually performed during a particular time period.
EV Formula?
Earned Value (EV) = % completed x Planned Value (PV)
AC stands for?
Actual Cost.
Actual Cost (AC)?
Actual Cost (AC) refers to the total amount of costs incurred while accomplishing work performed, either during completion of a schedule activity or during the completion of a WBS component. Actual cost is calculated and documented once the work is complete. In other words, AC indicates the actual money that has been spent for work that has been completed.
SV stands for?
Schedule Variance
Schedule Variance (SV) formula?
- Schedule Variance (SV = EV-PV)
- A positive SV indicates that the project is ahead of schedule.
- A zero SV indicates that the project is on schedule.
- A negative SV indicates that the project is behind schedule.
SPI stands for?
Schedule Performance Index (SPI)
Schedule Performance Index (SPI) formula?
- Schedule Performance Index (SPI = EV/PV)
- An SPI number greater than 1.0 indicates that the project is ahead of schedule.
- An SPI of 1.0 means the project is on schedule.
- An SPI number less than 1.0 indicates that the project is behind schedule.
Schedule Control Chart?
Another tool you can use to illustrate schedule performance is the schedule control chart. This
chart can be used to show trends in schedule performance. The following graphic is an example of a
schedule control chart plotting the variance in the schedule and shows that the project started behind schedule and that corrective action was probably taken to bring the project back in line with planned schedule estimates.
Gantt Chart?
A Gantt chart is an effective tool for providing up-to-date summary information and can be extremely helpful for analyzing the project’s overall time performance. The Gantt chart also shows when milestones are scheduled and if those critical dates are still on track. Using the approved schedule baseline as the standard for measuring progress, the project manager can collect reporting information for each activity and use a Gantt chart to summarize data.