18 | Closing the Project Flashcards
In this lesson, you will perform project closure. • Deliver the final product. • Close project procurements. • Close a project.
Accepted Deliverables?
Accepted deliverables are all deliverables that are completed, accepted, and formally signed-off. The
deliverables that have been formally signed-off or acknowledged by the sponsors or customers are
moved toward project closure.
The Final Product, Service, or Result Transition?
The final product, service, or result transition is the process of transferring the final product that the project was authorized to produce. The final product is usually reviewed for completeness and accuracy before it can be transitioned to its recipients.
Procurement Audits?
A procurement audit is a formal evaluation of the effectiveness of the procurement process itself.
The goal of the audit is to establish a record that may be used to shape procurement practices in other contracts for this project or for other projects. This audit considers the following elements of the procurement process:
- Make or Buy Analysis.
- Preparation of the procurement SOW and procurement documents.
- Selection of selected vendors.
- Adequacy of the procurement contract.
- Contract administration
Procurement Audit Lessons Learned?
The lessons learned from a procurement audit can be invaluable information for future contracts. For example, the contract structure or payment terms that seemed appropriate at the start of the contract may have acted as disincentives to performance during the contract itself. By including as much anecdotal detail in the lessons learned as possible, you help others in the organization apply
the learning to their situations.
Negotiated Settlements?
Negotiated settlements are undertaken to arrive at a final equitable settlement for all outstanding issues, claims, and disputes by negotiation. The parties may resort to Alternative Dispute Resolution (ADR), which includes mediation and arbitration, if settlement cannot be achieved through direct negotiations held between the parties.
Closed Procurements?
Closed procurements are usually a formal written document between the buyer and the seller stating that no considerations are pending from either party. This can be done whenever a procurement contract is satisfied and can happen on a rolling basis throughout the project. The
buyer receives what was expected and is satisfied; the seller receives the payment and other aspects as prescribed in the contract. The contract spells out the terms and conditions for contract acceptance and closure. These terms and conditions are usually included in the procurement management plan.
What are the 2 special issues in contract closeout?
- Incomplete contract closeout
2. Vendor staff evaluations
Incomplete contract
closeout?
• Contracts may be terminated early due to vendor nonperformance or
through no fault of the vendor whatsoever.
• If a project is shut down prematurely due to issues within the customer or project organization, how does that impact contract closeout? In this situation, the contract itself will probably provide guidance as to how to deal with early termination.
• For example, the contract may have a clause that specifies that either side may withdraw from the contract with a 30-day written notice to the other side. During the 30-day notice period, the vendor may continue working on the project, tying up loose ends, taking receipt
of material ordered for the project, and so forth. Once the project has been terminated, the project manager should take whatever steps are necessary to provide the appropriate written notice as soon as possible, in order to start the termination clock.
• In addition, an explanatory call to the vendor in advance of the written notice is an expected courtesy. If the contract ties payment to specific deliverables, the procurement audit should verify that the deliverables were received as specified and that the invoices reflect
only those deliverables that were received. Issues of time, cost, and quality are still relevant.
- Be sure to evaluate these issues based on the version of the deliverable you are paying for, rather than for the final deliverable. For example, say the vendor was contracted to supply a beta version of the product in January and a final version in March. But the project was canceled in February.
- The product quality audit should be based on whether it met the specifications for a beta product, not for a final product
Vendor staff
evaluations?
- In some cases, vendors will request that you participate in evaluating their staff members who are participating in your project.
- In other cases, you may wish to send letters of commendation to a vendor, in order to recognize the performance of some of their staff members.
- Your organization may have a policy that limits your participation in evaluating the ongoing performance of vendor staff. You should consult this policy before providing any sort of written performance evaluation.
- Most organizations allow letters of commendation that recognize the contribution of particular vendor staff members. This practice is highly motivating to the vendor staff.
- Usually, a copy is sent both to the staff member individually and to the vendor organization.
Administrative Closure?
Administrative closure involves verifying and documenting project results to formalize project or
phase completion on all aspects. During the administrative closure process, the project team gathers
and updates project documentation and relevant records and reports. Project results are compared with customer and stakeholder expectations and requirements. A properly completed administrative closure process ensures that:
- The project or phase requirements were met and formal acceptance was granted.
- The project objectives were completely met.
After the administrative closure is complete, you should conduct a project evaluation whereby you will review the original proposed financial and operational benefits and determine whether or not they have been achieved over time. If they have not been achieved, you should evaluate and determine if further action is required.
Project Records to Archive?
During administrative closure, it may be beneficial to archive selected project records such as:
• The project management plan with its subsidiary plans and supporting detail.
• Project performance records, audit reports, and financial records.
• Contract documentation as completed in closed procurements.
• Copies of all relevant communication, status reports, meeting minutes, and change requests.
• Relevant project databases.
• Staff evaluations.
• Lessons learned reports and the final project report.
• Formal acceptance documentation.
It may be helpful to construct a list of outstanding items that must be resolved, addressed, or completed before the customer will accept the final work results. Include the actions taken to resolve any outstanding issues and any time frames associated with completion
Lessons Learned Reports?
Lessons learned reports are documents that capture salient and helpful information about the work done in a project; they identify both the project team’s strengths and areas for improvement. They can be formal or informal, depending on the organizational norms or requirements. The lessons learned reports can be built by contributions from the project team throughout the project, and edited into a clean document during closing. This minimizes the need for contributors to recall
details at the end of the project. Lessons learned reports will be beneficial to future project teams. Having this knowledge base enables project teams to capitalize on work that has already been done, avoid repeating mistakes, and benefit from ongoing organizational learning.
What are the 7 considerations of lessons learned?
- Scheduling lessons learned
- Conflict management lessons learned
- Vendor lessons learned
- Customer lessons learned
- Strategic lessons learned
- Tactical lessons learned
- Other aspects of lessons learned
Scheduling lessons learned?
These include any relevant scheduling problems or issues. They also document the management strategies that were implemented to deal with schedule or resource constraints. Capture beneficial approaches to implement as new best practices.
Conflict management lessons learned?
These include any issues that arose within the team or between the team and customers. They include documentation of the nature and source of the conflict and the impact that the conflict had on the project. The documentation should also specify how management intervened in response to the conflict.