5.3 Variable overhead variances & Fixed production overhead cost variances Flashcards

1
Q

Variable overhead variances

A

Variable overhead total variance (difference between variable overhead that should be used for actual output and variable production overhead actually used)
- Variable overhead expenditure variance (paying more or less than expected per hour of variable overheads, which hrs depends on recovery base)
- Variable overhead efficiency variance (using more or less variable overheads per unit than expected)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Variable overhead total variance

A

Actual cost for Actual units
Less: Actual units X Std cost per hr

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Variable overhead expenditure variance

A

Actual cost for Actual hrs worked
Less: Actual hrs worked X Std cost per hour

(when recovery base is labour hrs and there is idle time, calculated using active hours worked)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Variable overhead efficiency variance

A

Actual hours for Actual units
Less: Actual units X Std hrs per unit
X Std rate per hour

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Fixed production overhead cost variances

A

Fixed overhead total variance
- Fixed overhead expenditure variance
- Fixed overhead volume variance
* Fixed overhead capacity variance
* Fixed overhead efficiency variance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Fixed production overhead total variance

A

Actual cost for Actual units
Less: Actual units X Std rate per unit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Fixed production overhead expenditure variance

A

Actual overhead
Less: Budgeted overhead

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Fixed production overhead volume variance

A

Actual units produced
Less: Budgeted units
X Std absorption rate per unit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

In absorption costing systems if the fixed overhead is absorbed based on hours then

A

The absorption rate per hour must be used instead of units:
Actual units X Std hrs per unit X Std absorption rate per hour
Less: Budgeted hours X Std absorption rate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

In absorption costing systems if the fixed overhead is absorbed based on hours then it can be split into:

A
  • Fixed overhead capacity variance - measures whether the workforce worked more or fewer hours than budgeted for the period
  • Fixed overhead efficiency variance - measures whether the workforce took more or less time than standard in producing their output for the period
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Fixed overhead capacity variance =

A

Actual hours X FOAR per hour
Less budgeted expenditure

  • If actual hours > budgeted hours = Favourable (greater capacity to produce units)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Fixed overhead efficiency variance =

A

Actual hours X FOAR per hour
Std hours for Actual production X FOAR per hour

If actual hours < std hours = Favourable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Potential causes of fixed and variable overhead variances:

A
  • Fixed overhead expenditure adverse variances are caused by spending in excess of the budget
  • Fixed overhead volume variances are caused by changes in production volume
  • Variable production overhead expenditure variances are often caused by changes in machine running costs
  • Fixed and variable production overheads efficiency variation causes are similar to those for direct labour efficiency variances
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Interdependence between variances means it might be necessary to look at several variances together not in isolation, for example:

A
  • Using cheaper materials will result in a favourable material price variance, but it might also increase wastage (adverse material usage) and reduce labour productivity (adverse labour and variable overhead efficiency)
  • Using more experienced labour to do the work will result in adverse labour rate variance but productivity might be higher resulting in favourable labour and variable overhead efficiency
  • Workers trying to improve productivity (favourable efficiency variance) in order to win a bonus (adverse rate variance) might use materials wastefully in order to save time (adverse materials usage)
  • Cutting sales prices (adverse sales price variance) might result in higher sales demand from customers (favourable sales volume variance)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

An operating statement is a

A
  • Top level variance report, reconciling the actual and budgeted profit for the period
  • Management will want unusual or unexpected items brought to their attention (exception reporting)
  • This will take the form of a reconciliation which highlights the variances between figures in as much detail as possible
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Variance analysis using ABC costing

A
  • ABC is a method for determining the std costs and will have implications for some of the variances calculated
  • The use of ABC is most likely to impact overhead variances
  • Typically std costs can be compared to actual and overhead expenditure and efficiency variance calculated