10.1 Relevant costs and revenues Flashcards
1
Q
Relevant costs and revenues are
A
- Those costs and revenues that change as a direct result of a decision taken
- Decisions will generally be based on taking the decision that maximises shareholder value
2
Q
Relevant costs and revenues have the following features
A
- They are future costs and revenues (not possible to change what happened in past)
- They are incremental or differential - only the change in costs and revenues that occur as a direct result of decision taken are relevant
- They are cash flows - they must be cash flows arising as a direct consequence of the decision taken, not profits, as profits can be manipulated (excludes items that don’t involve cash flows)
3
Q
Two specific types of relevant costs:
A
- Opportunity costs
- Avoidable costs
4
Q
Opportunity cost represents the
A
- Value of the best alternative that is forgone in taking the decision
- It emphasises that decision making is concerned with alternatives and the cost of taking one decision is the profits forgone by not taking another
- Therefore consideration must be given to profits or contributions which could be earned from alternative uses of resources
- Effects on cash flows of the whole org must be considered (not single department)
5
Q
Avoidable costs are
A
- Costs that would not be incurred if the decision did not go ahead
- Such as the costs that would be saved by shutting down a department (eg labour, rent, etc)
6
Q
Non relevant costs include
A
- Sunk costs
- Committed costs
- Fixed costs
- Depreciation
- Notional costs
7
Q
Sunk costs are
A
- Already incurred and therefore not relevant to decision making and should be ignored (can’t change the past)
- Aka irrecoverable costs and eg: costs incurred in developing a new product, money can’t be recovered if further development is abandoned
8
Q
Committed costs are
A
- Costs that will be incurred in the future as a result of decisions taken in the past that cannot now be changed (ie. unavoidable in the future)
- It will be incurred regardless of the decision being taken and therefore not relevant
- Eg ordered packing for new product will still need to pay for it even if decided not to proceed with product
9
Q
Fixed costs should be
A
- Treated as a whole and only where relevant
- Fixed overheads that are absorbed / charged / allocated / apportioned to a project should be ignored
- The amount of overhead to be absorbed by a particular cost unit might alter because of the decision, however this is as a result of the companys cost accounting procedures for overheads
- If the actual amount of overhead incurred will not alter then it is not relevant
- Only extra / incremental changes in fixed overheads should be included in decisions
10
Q
Depreciation is an
A
- Accounting adjustment to spread the original cost of an asset over its useful life but does not result in cash flows
- Depreciation / net book values should never be treated as a relevant cost for decision making
11
Q
Notional costs are
A
- Costs that will not result in an outflow of cash either now or in the future
- Eg head office charging theoretical rent to branches
12
Q
Incremental revenues are the
A
- Differences in revenue between the alternatives
- Matching the incremental costs against the incremental revenues will produce a figure for the incremental gain or loss between the alternatives
13
Q
The relevant cost of materials
A
- There are a number of alternative costs which could be relevant for materials, such as replacement cost, net realisable value or opportunity cost, depending on the relevant situation
- Are materials in inventory - No - Relevant cost = Cost of purchase
- Will they be replaced - Yes - Relevant cost = Replacement cost
- Will it be used for other purposes - Yes - Relevant cost = Opportunity cost; No - Relevant cost = Net realisable value
14
Q
The relevant cost of labour
A
- Key question is whether spare capacity exists
- If yes - Existing workforce are idle and being paid regardless = Nil
- If no and only option is to hire in additional workers = Cost to hire in workers
- If no and only option is to transfer existing workers from alternative projects = Opportunity cost (contribution)
- If no and choice of hiring in or transferring labour = Lowest cost
15
Q
The relevant cost of overheads
A
- Only relevant if they vary as a direct result of the decision taken