4B - Pre-Contract and Tendering Flashcards

1
Q

What is the process once you have tenders returned to you?

A
  • Assess each tender based on quality VS price - different jobs have different weightings.
  • Check for errors.
  • Reply to tenderers whether they are successful or not - list the tenderers at the end, but anonymously (you can give the tender prices but must remain unbiased)
  • In the public sector there are more strict rules and more weight on cost as it is publically funded.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is included in the tender package?

A

Documents and drawings included are:
* An invitation to tender letter
* Drawings
* Bill of Quantities
* Specification (often the drawing legend)
* The form of tender/contract
* and sometimes the Designers Risk Assessment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is contained in a tender report?

A

This is produced by the quantity surveyor and outlines process and results:
* Forms of tendering used
* List of tenderers
* Range of tender prices
* Notes of obvious errors and modifications
* Amendments to the tender during the tender period
* Recommendation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are restrictions on local authorities during the tender process?

A

Even considering quality, landscape architects have to select the tenderer with the lowest price. All tenderers should be of equal quality due to the shortlisting process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How do LPAs go about tendering?

A

Depending on the size of the project:
* Use Find a Tender service
* Framework agreements - whereby contractors tender to be on the framework and if accepted they don’t tender for previous jobs
* Invitation to tender via BALI - private sector

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

On a small landscape design scheme, how would you go about preparing the bill of quantities and specification?

A

If the project isn’t large enough to warrant a quantity surveyor, you would need to estimate the quantities of materials required, time needed and therefore cost implications, labour, and other factors. This could be aided by SPONS Architect and Builders price book.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is a specification?

A

This is a document usually prepared by the designer that describes the materials and workmanship required for a development. It does not include cost, quantity or drawn information and so needs to be read alongside other information such as bill of quantities, schedules or drawings. It can either be a performance spec. or descriptive.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is a bill of quantities and what does it typically contain?

A

A bill of quantities is a document used in tendering in the construction industry. Materials, parts and labour (and their costs) are itemised. It contains: preliminaries, measured works, prime cost and provisional sums.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How would you select a list of tenderers if working in an unfamiliar region?

A

I would begin by asking colleagues, clients, or other consultants and then checking the BALI website.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What factors would you consider when deciding on the most suitable tendering method?

A

The degree of cost certainty, quality, time efficiency that the project / client requires.
The tender method may be determined by the chosen procurement method, for example framework agreements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The client has asked you to provide a shortlist of contractors for a construction project. How would you find suitable contractors?

A

I would make recommendations based on my past experience, then ask colleagues, clients or other professionals for recommendations. Then I would check the BALI website or if in a public sector project, use a framework agreement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How would you ensure a contractor was suitable for a project?

A

I would check their quality assurance and Health & Safety procedures, financial standing and resources. It might also be worth requesting references, asking questions or for a portfolio of similar projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the different tendering methods?

A

Open tendering: any contractor can submit a tender following advertisement
Selective tendering: Contractors can submit a tender by invitation
Negotiated tendering: one contractor is approached directly and submits a tender following negotiation
Serial tendering: Contractors can submit a tender for a series of similar, minor works projects
Framework tendering: allows shortlisted contractors signed up to the framework agreement to bid for projects over a fixed period of time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is single stage tendering?

A

Single stage tendering is the more conventional process. Tenders are sought based on tender documents and production information (all info required to calculate a price), assessed and the contractor is appointed using defined criteria such as cost and quality.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is two stage tendering?

A

Two stage tendering is used when an early appointment of a contractor is necessary so the design won’t be developed enough for an accurate cost.
First stage - similar to single stage but less information is provided and the preferred bidder is selected (“limited appointment”). The appointment is then dependent on the second stage based on the proposed programme, method statement, preliminaries, and pricing etc.
Second stage - negotiation between client and preferred bidder.
Design team and contractor finalise design and the contract sum is only established at the end of the second stage.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

When might a two stage process be used?

A

A two stage process might be used for projects with time constraints, for example design and build contract for a new school.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is the process for open tendering?

A

The project is advertised, for example on ‘Find a Tender’ portal.
Anyone in the European market can tender.
Tender is selected based on price - the most economically advantageous tender is chosen.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

When would you use negotiated tendering?

A

When there is already a working relationship between the client and contractor and a specialist service is required.
Negotiated tendering can either be one or two stage.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What are the pros and cons of single stage selective tendering?

A

Pros:
Reduces abortive costs involved in estimating
All tenderers will be capable of works

Cons:
Higher cost involved as it is a more onerous process
No negotiation, therefore it is less flexible
Increased design team input

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What are the pros and cons of negotiated tendering?

A

Pros:
Early appointment of a contractor
Cost saving due to contractors expertise
Established relationship benefits

Cons:
Higher price of tenders because they pre-empt negotiation and there is less competition
Design uncertainty, therefore a cost uncertainty

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What can you do if an error is discovered in a returned tender?

A

You can either offer the contractor a confirm or withdraw or confirm or amend.
If they choose confirm or withdraw: this is usually for public sector procurement due to the tender price not being able to change. If they withdraw, the next cheapest is selected.
If they confirm or amend, a correction of the tender prices is permitted. If amended they can still be successful if their price is the lowest.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What is the tender process?

A
  1. Contact the potential tenderers to ask if they’d like to submit (out of courtesy)
  2. Ask tenderers to complete an expression of interest
  3. Follow up with a selection questionnaire so the tenderer can prove capacity early and reduce any non compliant tenders.
  4. Invitation to Tender issued to the tenderers.
  5. Tenders returned (contractors work through the ITT and prices the BoQ)
  6. Checking of tenders and notification (late tenders are rejected, QS examiens to detect any errors and scores are returned based on the selection criteria)
  7. Tender report and recommendation (QS provides report outlining the process and results and makes an offer)
  8. Acceptance of tender (offer acceptance initiates the contract)
  9. Notification of tenderers (inform unsuccessful tenderers)
  10. Contract preparation (full documents are prepared and signed, Contract Award milestone)
23
Q

What is the production of information?

A

Production of information is essentially the same as contract documents: Qualitative information such as plans and drawings and quantitative information such as the BoQ and specification.

24
Q

What is the difference between a descriptive specification and a performance specification?

A

Descriptive: describes the quality of materials, workmanship, material dimensions, finish and construction method can include specific products such as make and model of benches.
Performance: describes the desired result, i.e. ‘a bench’.

25
What would you have to consider when specifying materials and products?
Aesthetics Cost vs Budget Availability and lead times Compliance and certificates e.g. BS, BREAAM, FSC etc.
26
What is the purpose of a Bill of Quantities?
Enables tenders to be submitted based on the same information Assists the same contractor in selecting material and labour It forms the basis for valuing alterations Assists in preparing interim valuations and future estimates Important link between design and construction Used as a cost estimate pre-tender
27
What is a bill of quantities?
An itemised list of materials and parts required for a construction project.
28
What are the contents of a bill of quantities?
Preliminaries (sets out contractors working arrangements) and the measured works (quantities summarised from drawings and the specification.
29
In the Bill of Quantities, what is prime cost, provisional sum and contingency sum?
Prime cost is an exact sum for works and details known at tender Provisional sum is estimated by the QS when work cannot be accurately quantified at tender. This could include works below the ground. In a Defined Sum the risk is carried by the contractor. If Undefined, the the risk is carried by the client. Extensions of time and additional costs can occur. Contingency sums allow for unforeseen works and are a specific percentage (2.5% or 5%) of the tender cost. This can be released with the authority of the QS or CA.
30
What takes precedence if there is a discrepancy between product information?
For discrepancies between the bill of quantities, specification and qualitative information it depends on the contract. normally the bill of quantities would take precedence corrections resulting in changes to rates or quantities were resulting variation. Contract administrator will then decide which takes precedence if there are no priced work schedules.
31
Is a bill of quantities always required?
No. In some cases, bills of approximate quantities, schedules of works or schedule of rates is sufficient.
32
What is the role of a contract administrator?
They advise the client Prepare contract documents Advise on contract responsibilities Chair pre-start and progress meetings Contract administration throughout construction phases Visits to the site to check progress Issue instructions and carry out variations Consider any claims Collate schedule of defects And issue progress and pay certificates
33
What is the overview and key principles of pre-contract and tendering?
Technical design Procurement strategy Tendering process example selective or open Post tender period
34
What RIBA work stage covers detailed design to production information?
Stage four technical design
35
When submitted documents for tender what technical design information may be included?
36
Depending on the level of detail and form of procurement, what types of specification may be used?
Descriptive or performance Descriptive includes additional information such as the manufacturer of the size the colour Performance describes only what the item is, i.e. a bench
37
What regulations should you be aware of when producing technical specification for public contract documents?
Public contract regulations
38
What are some preliminaries?
Preliminaries of works that are priced by the contractor for work not covered elsewhere in the tender documents. These form part of the bill of quantities and can include things like: Access Site security Statutory approvals Site meetings And day works
39
What are dayworks?
Daywork when a contractor is paid for instructed work based on the cost of labour, materials and plant (plus a markup for overheads and profit). These cannot be priced into the bill of quantities. It is generally used when work cannot be valued in the normal way for example there is no comparative rates in the bill of quantities and a pro rata method of pricing cannot be used such as an unforeseen works. This method of pricing can be open to exploitation so it is advisable to put monitoring and controlling procedures in place.
40
What alternatives to the bill of quantities exist?
Bill of approximate quantities this comes earlier in the design process before a design is final Schedule of works when a contractor quantifies and prices work based on specification and drawings A schedule of rates when work required is not known at the outset
41
What are the pros and cons of a schedule of works?
Pros Fixed price lump sum Contractor produces measurement so there’s less risk to the client Cons Design must be reasonably well advanced variations can be difficult to agree with a contractor More difficult to compare tenders
42
What is the role of a quantity surveyor?
Prepare the bill of quantities Prepare pretender estimates Check tenders and produce the tender report Advise on general financial aspect of project Involved in any design variations during construction Measuring works carried out on site and periodically valuing all material on site Producing monthly cost reports
43
What is included in a tender report?
Statement of what the project comprises Form of tendering used List of tenderers and any that have withdrawn Range of prices Quality assessments, if applicable Amendments, if applicable Comment on current rates within the market Recommendations
44
What would inform your tender decision?
In theory, the lowest tender should win even in the private sector as all tenders should in theory be suitable. this is insured through the form of procurement and the tender method and shortlisting. However on project qualities is a priority it may be better to recommend tenders that stand out for quality and experience.
45
What happens once a tender report and recommendation to the client has been made?
They offer from the selected contractor is accepted, signed in writing and this initiates the contract. Unsuccessful tenders are informed and given feedback tenders can be listed in alphabetical order with price in ascending order but without names.
46
Where would you refer to for further information for guidance and model forms for the tendering process?
JC tendering practice note 2012 - this guidance covers the selective process, including single stage, two stage, competitive dialogue, tendering, and prequalification and assessment. It also covers the preliminary enquiry, invite to tender and assessment and award. The NBS guide to tendering 2011 - this covers procurement, tender assessment and contract award and focuses on single stage selective tendering
47
What is a prequalification questionnaire?
In a single stage tender this is used to prove the capability of each tenderer. It includes things like experience, management structure, competence and resources and environmental credentials.
48
How would you put together a list of potential tenders for a client?
Previous experience Ask colleagues in the professional or the clients Look at clients previous preferred contractors And check BALI website
49
Explain the tendering process… for selective single stage
Tenderers are shortlisted Selection questionnaire Invitation to tender Tender return, which is then checked Tender report and recommendation
50
What is included in the invitation to tender documents?
There is a form setting out project and location, drawing list, specification and bill of quantities
51
What is involved in the tender return stage?
Contractor submit the priced bill of quantities Tender returned within 28 days for private, 40 for public Formal opening procedures with witnesses at 12 pm Late tender rejected Quantity surveyor examines to detect errors prior to acceptance Quantity surveyor scores costs
52
What happens if errors are found by the quantity surveyor in the tender return?
The quantity surveyor would notify the contract administrator who would notify the tenderer with the option to confirm or withdraw (public) or confirm or amend (private)
53
What should a tender report contain?
Statement of what the project comprises Form of tendering used List of tender and any that have withdrawn Range of tender prices Quality assessments, if applicable Notes of obvious errors Amendments, if applicable Comment on current market rate Recommendation