4A - Project Plans, Budgets and Works Stages Flashcards
1
Q
What is the general programme of a construction project?
A
- Pre-start meeting
- Mobilisation period
- Date of possession (responsibility of the iste is transferred from the client to contractor)
- Construction phase (including regular site inspections, progress meetings, valuations etc.)
- Handover (following practical completion)
- Rectification and maintenance period
- Final completion
2
Q
What is the general agenda of a pre-start meeting?
A
- Intros-roles, responsibilities, contract details
- Project-description, site, special requirements
- Contract formalities
- Statutory matters - legislation, by-laws (e.g. TPOs)
- CCDM and Health & Safety
- Contractual matters - programme, site organisation
- Clerk of works
- Consultant matters
- Quantity surveyor matters
- Communications
- Meetings
3
Q
What is the general agenda of a progress meeting?
A
- Present & apologies
- Minutes of last meeting
- Any matters arising
- Contractors, clerk of works, consultants, QS reports
- Communications
- Contract completion date
- AOB
4
Q
What progress certificates exist?
A
Progress payment certificates
Practical completion certificate
Penultimate certificate (releases half the retention fee, normally 2.5%)
Certificate of making good
Certificate of final completion (releases the remaining retention fee)
5
Q
What are the RIBA Stages of Work?
A
- Strategic definition-work acquired by bid/design comp/direct appointment
- Preparation and brief
- Concept design
- Detailed design
- Technical design (finishing with appointment of contractor
- Construction (finishing with practical completion)
- Handover (finishing with final completion)
- In use