4. CDM Health & Safety Flashcards

1
Q

Name the duty holders within the CDM regulations

A

Client
Designers
Principal designers
Contractors
Principal contractors
Workers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are CDM Regs?

A

Construction Design and Management Regulations 2015
The main set of regulations for managing health and safety and welfare of construction projects. The overarching aim is to reduce risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What health and safety legislation should landscape architects be aware of at work?

A

Health and safety at work Act - the foundation of all health and safety legislation at work in the UK.
CDM Regs 2015

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

When would you need to notify HSE of accidents at work?

A

HSE must be notified for most types of incidents in the workplace, including accidents resulting in hospital treatment, death and anything requiring 8 or more days off work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the purpose of CDM?

A

The reduce risk
Good planning; avoiding, reducing and mitigation from start to finish
Appointing the right people for the right job
Ensure cooperation and coordination of work and people involved in construction
Ensure all necessary information and training is provided and supervision to carry out roles is a way that ensures health and safety
Ensures workers welfare and wellbeing is protected

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The main duties of the client under CDM are:

A

Management
1. Enable others involved to manage the health and safety risks appropriately
2. Includes providing pre construction info to contractors and designers
3. Appoint the correct people for each job at the right time
4. Ensure suitable welfare facilities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The main duties of a Principal Designer under CDM are:

A

An individual/organisation appointed by the client to take control of the pre construction phase
1. Plan manage and communicate health and safety in pre construction phase, taking into account risks like falls from height and working near water
2. Ensure those involved in pre construction communicate and cooperate when required.
3. Liaise with principal contractor during construction
4. Help and advise client

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The main duties of a designer under CDM are:

A

Individual/organisation involved in preparing or modifying designs for construction projects (or instructs others to do so)
1. All pre construction info must be taken into account and foreseeable health and safety risks eliminated, reduced or mitigated
2. Communicate and cooperate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The main duties of the principal contractor under CDM are:

A

Appointed by the client to plan, manage and monitor the health and safety during construction
1. Prepare written construction phase plan, implement and regularly review
2. Liaise with others, coordinate health and safety information
3. Consult and engage with workers and ensure welfare facilities are in place
4. Ensure everyone has the required induction training and information
5. Prevent unauthorised access to the site

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The main duties of a contractor under CDM are:

A

A contractor is anyone who directly employs or engages construction workers or manages the work.
1. Plan, monitor and manage all work
2. Ensure all workers have the appropriate skills, induction, training and information as well as support and welfare facilities.
3. Ensure access to the site is secure
4. Coordinate with other duty holders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The main duties of the worker under CDM are:

A

A worker is anyone working for/under the contractor on a construction site.
1. Only carry out work they have the appropriate skills, training, induction and experience for
2. Ensure they are always informed of the risks involved
3. Always follow site rules and procedures
4. Report issues
5. Cooperate with all others involved

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Do CDM regs cover soft landscape works?

A

Not if the project only involves soft works. Horticultural works are not considered construction.
If the soft landscape is part of a project which involved construction then CDM regs would apply.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

When do CDM Regs apply?

A

They apply to all construction projects in the UK.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What were the main changes to the CDM Regs in 2015?

A

CDM coordinator replaced with principal designer
Domestic clients now included in the Regs
Construction phase plan now required for every project
Makes note of the threshold for notifying HSE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Who is responsible for health and safety of a project?

A

During the construction phase, the principal contractor is responsible. Prior to this, it is the principal designer.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How would health and safety files be compiled in complex projects with multiple contracts?

A

A health and safety file will be compiled for each contract / phase.

17
Q

When is a project notifiable to HSE?

A

If a project lasts longer than 30 days and has at least 20 people working on site, or a project has over 500 person days. On commercial projects, it is the client that has to notify HSE (with an F10 form) and this has to be done before work begins.

18
Q

What documentation is needed under CDM?

A
  1. Pre construction information
  2. Construction phase plan
  3. Health and safety file