47 Process Reversed Flashcards
The process of developing A DOCUMENT that formally authorizes the existence of a project and provides the project manager with the authority to APPLY organizational RESOURCES to project ACTIVITIES.
Develop Charter
The process of IDENTIFYING the people, groups, or organizations that could IMPACT or be IMPACTED by a decision , activity, or outcome of the project; and ANALYZING and DOCUMENTING relevant information regarding their interests, involvement, inter-dependencies, INFLUENCE and potential IMPACT on project success.
Identify Stakeholders
The process of DEFINING, PREPARING, and COORDINATING all subsidiary plans and integrating them into a comprehensive project management plan. MAY include integrated baselines and subsidiary plans…
Develop Project Management Plan
The process of CREATING a scope management plan that documents how the project scope will be defined, validated and controlled.
Plan Scope Management
The process of DETERMINING, DOCUMENTING and MANAGING stakeholder needs and requirements to meet project objectives.
Collect Requirements
The process of DEVELOPING a detailed description of the project and product.
Define Scope
The process of SUBDIVIDING project deliverables and project work into smaller, more manageable components.
Create WBS
The process of ESTABLISHING the policies, procedures and documentation for PLANNING, DEVELOPING, MANAGING, EXECUTING, and CONTROLLING the project schedule.
Plan Schedule Management
The process of IDENTIFYING and DOCUMENTING the specific actions to be performed to produce the project deliverables.
Define Activities
The process of IDENTIFYING and DOCUMENTING relationships among the project activities.
Sequence Activities
The process of ESTIMATING the type and quantities of material, human resources, equipment, or supplies required to perform each activity.
Estimate Activity Resources
The process of ESTIMATING the number of work periods needed to COMPLETE individual activities with the estimated resources.
Estimate Activity Duration
The process of ANALYZING activity sequences, duration, resource requirements, and schedule constraints to CREATE the project schedule model.
Develop Schedule
The process of IDENTIFYING quality requirements and/or standards for the project and its deliverables and DOCUMENTING how the project will DEMONSTRATE compliance with quality requirements.
Plan Quality Management
The process of IDENTIFYING and DOCUMENTING project roles, responsibilities, required skills, reporting relationships, and CREATING a staffing management plan.
Plan Human Resources Management
The process of DEVELOPING an appropriate approach and plan for project communications based upon stakeholder’s informational needs and requirements, and available organizational assets.
Plan Communications Management
The process of DEFINING how to CONDUCT risk management activities for a project.
Plan Risk Management
The process of DETERMINING which risks may AFFECT the project and DOCUMENTING their characteristics.
Identify Risks