3M Flashcards

1
Q

Who is the 3M manager on board CVN70?

A

XO

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Who sponsors the Navy’s 3M program?

A

CNO

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What color is a danger tag?

A

Red

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What color is a caution tag?

A

Yellow

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How often is an MRC with periodicity Q-2 required to be accomplished?

A

Quarterly

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the periodicity code R stand for?

A

Situational

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What best represents the main purpose of 3M?

A

To ensure maximum equipment readiness meeting minimum specifications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the procedure in verifying a MRC against the work center PMS manual?

A

MRC to MIP, MIP to LOEP, LOEP to ROC, and check the current force revision

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What does MIP stand for?

A

Maintenance Index Page

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What does SPMIG stand for?

A

Standard PMS Material Identification Guide

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the SPMIG

A

5 digit number used to identify tools, parts, or material listed on the MRC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is SKED used for?

A

Schedule, track, and assign PMS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What SKED PMS schedule show all the maintenance requirements to be completed for the week?

A

Weekly

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What sheet is signed by the maintenance person after completion of the maintenance?

A

13-week report

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Who annotates on the 13 week report/flip page the reason for non-accomplishment of maintenance requirements?

A

WCS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What color is a classified MRC?

17
Q

What are the conditions for a piece of equipment to be placed in IEM status?

A
  • Inactive for corrective maintenance
  • Inactive for 30 days or more
  • Stored at a location off the ship
18
Q

What are the authorized calendar periodicity codes?

A
D- daily
2D - every 2nd day
3-D - every 3rd day
W - weekly
2W - every 2nd week
3W - every 3rd week
M - monthly
2M - every 2nd month
Q - quarterly
4M - every 4th month
S - semi-annually
8M - every 8th month
A - annually
18M - every 18 months
19
Q

What is the forces afloat safety manual?

A

OPNAVINST 5100.19E

20
Q

What is JSN?

A

Job Sequencing Number

21
Q

What are the three parts of a Job Control Number?

A
  • UIC (Unit Identification Code)
  • Work Center
  • JSN (4 digit number that starts at 0001)
22
Q

What color is an out of commission label?

23
Q

What color is an out of calibration label?

24
Q

Who does the maintenance person notify when there is a problem conducting PMS?

25
What does the LOEP provide?
A listing of maintenance index pages assigned to each work center
26
What is the Ship's Maintenance Management System Manual?
OPNAVINST 4790.4C
27
Who is the 3M functional manager on board?
3M Coordinator
28
If an MRC requires a maintenance person of a certain rate to perform maintenance, can someone of another rate be assigned to perform the maintenance?
Yes, if the MP possesses the required skill set
29
When an MRC calls for a certain NEC for the maintenance person to perform the maintenance can anyone else be assigned the maintenance?
NO
30
What is the four-digit code located at the lower right corner of the MRC used in cataloging MRC's?
Syscom Control Number
31
What does the MSDS contain?
Information about materials: - composition - chemical and physical characteristics - health and safety hazards - precautions for safe handling and use
32
How many weeks worth of accountability logs are required to be maintained in the 13 week accountability file?
14 ; 13 previous weeks and the current week
33
Who maintains the PMS master file?
3M Coordinator (3MC)