Q

What is the LCO and APPLICABILITY of Technical Specification 3.8.1, AC Sources-Operating?

A

LCO:
The following AC electrical power sources shall be OPERABLE:
A. Two qualified circuits between the offsite transmission network and the onsite Class 1E AC Electric Power Distribution System; and
B. Three diesel generators (DGs).

APPLICABILITY: MODES 1, 2, and 3.
NOTE
Division 3 AC electrical power sources are not required to be OPERABLE when High Pressure Core Spray System is inoperable.
******

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the one hour, or less, actions associated with Technical Specification 3.8.1, AC Sources-Operating?

A

NOTE********
LCO 3.0.4.b is not applicable to DGs
**********
Condition A: One required offsite circuit inoperable - Perform SR 3.8.1.1 OPERABLE required offsite circuit - 1 hour

Condition B: One required DG inoperable - Perform SR 3.8.1.1 OPERABLE required offsite circuit - 1 hour

Condition G: Three or more required AC sources inoperable - Enter LCO 3.0.3 - Immediately

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the LCO and APPLICABILITY of Technical Specification 3.8.2, AC Sources-Shutdown?

A

LCO:
The following AC electrical power sources shall be OPERABLE:
A. One qualified circuit between the offsite transmission network and the onsite Class 1E AC electrical power distribution subsystem(s) required by LCO 3.8.8, “Distribution Systems-Shutdown”:
B. One diesel generator (DG) capable of supplying one division of the Division 1 or 2 onsite Class 1E AC electrical power distribution subsystem(s) required by LCO 3.8.8; and
C. One qualified circuit, other than the circuit in LCO 3.8.2.a, between the offsite transmission network and the Division 3 onsite Class 1E electrical power distribution subsystem, or the Division 3 DG capable of supplying the Division 3 onsite Class 1E AC electrical power distribution subsystem, when the Division 3 onsite Class 1E electrical power distribution subsystem is required by LCO 3.8.8.

APPLICABILITY:
MODES 4 and 5,
During movement of recently irradiated fuel assemblies in the primary containment or fuel handling building.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the one hour, or less, actions associated with Technical Specification 3.8.2, AC Sources-Shutdown?

A

NOTE**
LCO 3.0.3 is not applicable
**
****

Condition A:
LCO Item A is not met -
NOTE*
Enter applicable Condition and Required Actions of LCO 3.8.8, when any required division is de-energized as a result of condition A.
**
*******
-Declare required feature(s) with no offsite power available from required circuit inoperable - Immediately
OR
Suspend CORE ALTERATIONS - Immediately
AND
Suspend movement of recently irradiated fuel assemblies in the primary containment and fuel handling building - Immediately
AND
Initiate action to suspend operations with a potential for draining the reactor vessel (OPDRVs) - Immediately
AND
Initiate action to restore required offsite power circuit to OPERABLE status - Immediately

Condition B:
LCO item B not met -
Suspend CORE ALTERATIONS - Immediately
AND
Suspend movement of recently irradiated fuel assemblies in the primary containment and fuel handling building - Immediately
AND
Initiate action to suspend operations with a potential for draining the reactor vessel (OPDRVs) - Immediately
AND
Initiate action to restore required offsite power circuit to OPERABLE status - Immediately

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the LCO and APPLICABILITY of Technical Specification 3.8.3, Diesel Fuel Oil, Lube Oil, and Starting Air?

A

LCO: The stored diesel fuel oil, lube oil, and starting air subsystems shall be within limits for each required diesel generator (DG).

APPLICABILITY: When associated DG is required to be OPERABLE.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the one hour, or less, actions associated with Technical Specification 3.8.3, Diesel Fuel Oil, Lube Oil, and Starting Air?

A

Condition F: One or more DGs with diesel fuel oil, lube oil, or starting air subsystem not within limits for reasons other than condition A, B, C, D, or E - Declare the associated DG inoperable - Immediately

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the LCO and APPLICABILITY of Technical Specification 3.8.4, DC Sources-Operating?

A

LCO: The Division 1, Division 2, and Division 3 DC electrical power subsystems shall be OPERABLE.

APPLICABILITY: MODES 1, 2, and 3.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the one hour, or less, actions associated with Technical Specification 3.8.4, DC Sources-Operating?

A

Condition B: Division 3 DC electrical power subsystems inoperable - Declare High Pressure Core Spray System Inoperable - Immediately

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the LCO and APPLICABILITY of Technical Specification 3.8.5, DC Sources-Shutdown?

A

LCO:
The following DC electrical power subsystems shall be OPERABLE:
A. One Class 1E DC electrical power subsystems capable of supplying one division of the Division 1 or 2 onsite Class 1E electrical power distribution subsystem(s) required by LCO 3.8.8, “Distribution Systems-Shutdown”;
B. One Class 1E battery or battery charger, other than the DC electrical power subsystem in LCO 3.8.5.a, capable of supplying the remaining Division 1 or Division 2 onsite Class 1E DC electrical power distribution subsystem when required by LCO 3.8.8; and
C. The Division 3 DC electrical power subsystem capable of supplying the Division 3 onsite Class 1E DC electrical power distribution subsystem, when the Division 3 onsite Class 1E DC electrical power distribution subsystem is required by LCO 3.8.8.

APPLICABILITY:
MODES 4 and 5,
During movement of recently irradiated fuel assemblies in the primary containment or fuel handling building.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the one hour, or less, actions associated with Technical Specification 3.8.5, DC Sources-Shutdown?

A

Condition A:
One or more required DC electrical power subsystems inoperable -
Declare affected required feature(s) inoperable - Immediately
OR
Suspend CORE ALTERATIONS - Immediately
AND
Suspend movement of recently irradiated fuel assemblies in the primary containment and fuel handling building - Immediately
AND
Initiate action to suspend operations with a potential for draining the reactor vessel (OPDRVs) - Immediately
AND
Initiate action to restore required DC electrical power subsystems to OPERABLE status - Immediately

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the LCO and APPLICABILITY of Technical Specification 3.8.6, Battery Cell Parameters?

A

LCO: Battery cell parameters for the Division 1, 2, and 3 batteries shall be within limits.

APPLICABILITY: When associated DC electrical power subsystems are required to be OPERABLE.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the one hour, or less, actions associated with Technical Specification 3.8.6, Batter Cell Parameters?

A

NOTE
Separate Condition entry is allowed for each battery.
******
Condition A: One or more batteries with one or more battery cell parameters not within Table 3.8.6-1 Category C limits - Verify pilot cell’s electrolyte level and float voltage meet Table 3.8.6-1 Category C - 1 hour

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the LCO and APPLICABILITY of Technical Specification 3.8.7, Distribution Systems-Operating?

A

LCO: Division 1, Division 2, and Division 3 AC and DC electrical power distribution subsystems shall be OPERABLE.

APPLICABILITY: MODES 1, 2, and 3.
NOTE
Division 3 electrical power distribution subsystems are not required to be OPERABLE when High Pressure Core Spray System is inoperable.
******

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the one hour, or less, actions associated with Technical Specification 3.8.7, Distribution Systems-Operating?

A

Condition D: One or more Division 3 AC of DC electrical power distribution subsystems inoperable-Declare High Pressure Core Spray System inoperable- Immediately

Condition E: Tow or more divisions with inoperable distribution subsystems that result in a loss of function-Enter LCO 3.0.3 - Immediately

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the LCO and APPLICABILITY of Technical Specification 3.8.8, Distribution Systems-Shutdown?

A

LCO: The necessary portions of the Division 1, Division 2, and Division 3 AC and DC electrical power distribution subsystems shall be OPERABLE to support equipment required to be OPERABLE.

APPLICABILITY:
MODES 4 and 5,
During movement of recently irradiated fuel assemblies in the primary containment or fuel handling building.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are the one hour, or less, actions associated with Technical Specification 3.8.8, Distribution Systems-Shutdown?

A

NOTE
LCO 3.0.3 is not applicable
******
Condition A: One or more required AC or DC electrical power distribution subsystem inoperable - Declare associated supported required feature(s) inoperable - Immediately
OR
Suspend CORE ALTERATIONS - Immediately
AND
Suspend movement of recently irradiated fuel assemblies in the primary containment and fuel handling building - Immediately
AND
Initiate action to suspend operations with a potential for draining the reactor vessel - Immediately
AND
Initiate actions to restore required AC and DC electrical power distribution subsystems to OPERABLE status - Immediately
AND
Declare associated required shutdown cooling subsystem(s) inoperable and not in operation - Immediately