What is the LCO and APPLICABILITY for Technical Specification 3.5.1, ECCS-Operating?
LCO: Each ECCS injection/spray subsystem and the Automatic Depressurization System (ADS) function of eight safety/relief valves shall be OPERABLE.
APPLICABILITY:
MODE 1
MODES 2 and 3, except ADS valves are not required to be OPERABLE with reactor steam dome pressure less than or equal to 150 psig.
What are the one hour, or less, actions associated with Technical Specification 3.5.1, ECCS-Operating?
Condition B: High Pressure Core Spray (HPCS) System Inoperable - Verify by administrative means RCIC System is OPERABLE when RCIC is required to be OPERABLE - 1 hour
Condition H:
HPCS and Low Pressure Core Spray Systems Inoperable
OR
Three or more ECCS Injection/spray subsystems Inoperable
OR
HPCS System and one or more ADS valves Inoperable
OR
Two or more ECCS injection/spray subsystems and one or more ADS valves inoperable
- ENTER LCO 3.0.3 Immediately
What is the LCO and APPLICABILITY of Technical Specification 3.5.2, ECCS-Shutdown?
LCO: Two ECCS injection/spray subsystems shall be Operable
APPLICABILITY:
MODE 4
MODE 5 except with the reactor vessel head and steam dryer storage/reactor well gate removed and water level greater than or equal to 22 ft 9 inches over the top of the reactor pressure vessel flange.
What are the one hour, or less, actions associated with Technical Specification 3.5.2, ECCS-Shutdown?
Condition C: Two required ECCS injection/spray subsystems inoperable - Initiate action to suspend OPDRVS - Immediately AND Restore one ECCS injection/spray subsystem to OPERABLE status - 4 hours
What is the LCO and APPLICABILITY of Technical Specification 3.5.3, RCIC System?
LCO: The RCIC System shall be OPERABLE
APPLICABILITY:
MODE 1
MODES 2 and 3 with reactor steam dome pressure >150 psig
What are the one hour, or less, actions associated with Technical Specification 3.5.3, RCIC System?
Condition A: RCIC System inoperable - Verify by administrative means High Pressure Core Spray System is OPERABLE - 1 hour