3.3.4 Critical Path Analysis Flashcards

1
Q

Critical path analysis

A

The process of planning the sequence of activities in a project in order to identify the most efficient way of completing an integrated task or project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

4 features of a critical path

A

Nodes, activities, duration, prerequisite

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Nodes

A

Circles representing a point in time, identified by the completion of start of an activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What do the three splits in the nodes mean

A

Left: number of node
Right top: earliest start time
Bottom right: latest finish time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Activities

A

Events of tasks that link to nodes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Duration

A

The time taken to complete the activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Prerequisite

A

The activities that must be completed before the next activity can start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The first node will always have an EST of…

A

Zero

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How do you calculate the EST

A

Add the duration of an activity to the EST of a previous node

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How do you calculate the LFT

A

Give the last node of the project an LFT, work backwards from right to left, subtract the duration of the activity from the LFT for that activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Float

A

The duration an activity can be extended or postponed so that the project still finished within the minimum time as calculated

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Formula for float

A

LFT - ACTIVITY DURATION - EST

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

critical path

A

Activities with a float of zero cannot be delayed wifhijr delayinf the entire project. Activities on the critical path have an equal EST and LFT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Strengths of critical path analysis

A
  • helps businesses meet deadlines - especially for time sensitive projects
  • some projects are expensive and complex so CPA minimised risk of missing deadline
  • allows businesses to plan ahead
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Weakness of critical path analysis

A
  • unforeseen incidents can cause delays despite completing CPA
  • time consuming to complete
  • less necessary if company is experienced in delivering similar projects
  • improve efficacy snd reduce time taken to complete a project which in turn reduces costs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly