3.3 - Decision-making techniques Flashcards
Critical path analysis
A process that identifies which activities are ‘critical’ and which activities are ‘float’ (activities that can be delayed without delaying project)
How can a critical path analysis be used?
- Helps identify how long a project will take
- Helps to schedule tasks
- Determines most efficient way to complete collection of small tasks
How to calculate the earliest start time
EST = EST of previous activity + duration of previous activity
Time series analysis
and components
Basic tool to forecast future activity levels and make decisions based on this forecast
- Trend (underlying movement of sales, up down etc, due to pop, tech etc)
- Seasonal (regular patterns within a year, e.g. sunscreen, swim costume, scarves etc)
- Cyclical (long-term variations due to economic changes e.g. booms/slumps)
- Irregular (unpredictable events e.g. covid)
Uses of time series analysis?
- Identifying trends
- Forecasting
- Unemployment
- Economic growth
- Foreign debt
- Trade figures
Moving average limitations
- Relies on past continuing & historical data not always a good indication of the future
- Rapid change/ short product life-cycle is misleading data
- Time-consuming
- Complex
- Only as reliable as data put in
- Doesn’t account for how recent data is
- Doesn’t link with corporate objectives
Time series forecasting
Technique for the prediction of events through a sequence of time
How is variation calculated
Actual sales - trend
(Sales - moving average)
Average cyclical variation points
Find the average of each cycle points variations
4 point moving average
Add 4 sales then divide by 4
Latest Finish Time
LFT of following activity - duration of following activity
What is float
When there is a difference between EST and LFT
0 float = critical
Free float
Found by taking the EST of the task at the start and duration of activity away from EST at the end
EST @ end of activity - duration - EST @ start of activity
(Spare time available without delaying next activity)
Total float
Found by taking the EST and duration from LFT
LFT - EST - duration
(Spare time available without delaying the whole project)
Dummy activity
- Used to purely show dependencies
- Not labelled as they take up no time/ resources