2211 - Technical Management Processes Flashcards
What are the 8 System Engineering Technical Management Processes
- Technical Planning,
- Requirements Management,
- Configuration Management,
- Technical Assessment,
- Decision Analysis,
- Risk Management,
- Interface Management
- Technical Data Management.
What establishes and evolves project plans, assesses progress against the plan, and evaluates and selects alternatives.
The Technical Management Processes
______________, as opposed to program planning, addresses the scope of the overall technical effort needed to develop system products.
Technical Planning
____________________is the Government’s foundation plan for Systems Engineering activities planned for use on a project.
The Systems Engineering Plan (SEP)
_____________schedules are based on key events, related tasks and relevant completion criteria for the applicable engineering work model.
Event-based
An ______________refers to the functional and physical characteristics required to exist at a common boundary between two or more systems, end products, enabling products or subsystems.
Interface
The two types of interfaces are:
- External
* Internal.
The government _____________and the project _____________will play key roles in the development of external interfaces because these may involve interfaces with systems outside the control of the contractor.
Program Office, IPT
Risk Management includes what key elements:
- Risk Identification;
- Risk Analysis;
- Risk Mitigation Planning;
- Risk Mitigation Plan Implementation;
- Risk Tracking.
What establishes and maintains consistency of a product’s attributes with its requirements and product configuration information?
Configuration Management (CM)
There are three formal technical baselines established for a system are:
- Functional,
- Allocated
- Product.
The product baseline is at the ________________ level.
component
What measures the current state of a given technical parameter and then estimates how it will evolve over a specific time period based on the planned technical development effort.
Technical Performance Measurement (TPM)
The _______________ should be independent of the Program Manager in making assessments.
Technical Authority
A _______________- provides a comprehensive description of a given product.
Technical Data Package (TDP)
Requirements change for a variety of reasons which can include:
- Emerging technologies
- Changing threats
- New laws and policies
- New missions
- Evolving user needs
The ______________is responsible for long term storage and retrieval of technical data.
program manager
What is the use of models, prototypes, simulators and stimulators to develop data as a basis for making managerial or technical decisions.
Modeling and Simulation (M&S):