21. Project Finance Flashcards

1
Q

Can you provide some examples of effective control procedures?

A

Cost Reports
Cash flows
Provisional Sums
Value Engineering

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a cost report?

A

A report that includes costs incurred at the time of the report, forecast of costs and risk allowances.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a cash flow?

A

This is a predicted forecast of the project expenditure.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are provisional sums?

A

Provisional sums are items that are not defined in enough detail for tenderers to accurately price.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is value engineering?

A

Value engineering is the process of reducing cost without significant compromise on quality or function.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the different types of provisional sums?

A

Defined - These are described in detail. The contractor is expected to have made allowance for them in programme, planning and pricing preliminaries.

Undefined - Less described. The contractor is not expected to have made allowance for them in programme, planning and pricing preliminaries.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Are you aware of any other provisional sums?

A

Provisional Quantities - Scope and specification is known but quantity is not.

Prime Cost - When the extent of works is known but the final specification is not.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Explain the JCT Standard Terms of Payment

A

-Contractor submits an application for payment before the Interim Valuation Date.
- Due date is 7 days thereafter
- Final date for payment is 14 days after the due date.
- The Contract Administrator has 5 days after the due date to issue the payment certificate.
- Client can issue a pay less notice a minimum of 5 days before the date of payment, setting out basis for its calculation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the different types of VE?

A
  • Omit sections of the works
  • Reduce the scope of works
  • Change the specification
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the final account?

A

This is the conclusion of the contract sum. It signifies the agreed amount that the employer will pay the contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly