16. Design and Specification Flashcards

1
Q

What is the RIBA Plan of Work?

A

The RIBA Plan of Work organises the process of briefing, designing, constructing and operating projects into 8 stages. It explains the stage outcomes, core tasks and information exchanges required at each stage.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the stages of RIBA Plan of Work?

A

Eight stages from 0-7

0 - Strategic Definition
1- Preparation and Briefing
2- Concept Design
3 - Spatial Coordination
4 - Technical Design
5 - Manufacturing and Construction
6 - Handover
7 - Use

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the main outcomes of Stage 0 - Strategic Definition?

A

Outcome: Best means of achieving the client requirements are confirmed.
Core tasks: Preparing client requirements.
Develop business case for feasible options including review of project risks and budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the main outcomes for Stage 1 - Preparation and Brief?

A

Outcomes: Project brief approved by the client and confirmed it can be accommodated onsite.

Core tasks: Prepare client brief including project outcomes, sustainability outcomes and spatial requirements. Undertake initial site information (surveys). Undertake feasibility studies.

Statutory processes: Source pre-application planning advise.
Initiate collation of health and safety Pre-construction Information.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the main outcomes for Stage 2 - Concept Design?

A

Outcome: Architectural concept approved by the client and aligned to the project brief.

Core tasks: Prepare architectural concept design aligned to cost plan and project strategies. Undertake design reviews with client and stakeholders.

Statutory processes: Obtain pre-application planning advise & submit outline planning application. Agree route to building regulations compliance.

Ensure: Updated cost plan. Signed off stage report by client.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the main outcomes of Stage 3 - Spatial Coordination?

A

Outcome: Architectural and engineered information spatially coordinated.

Core tasks: Undertake design studies, engineering analysis and cost exercises aligned to updated cost plan and project strategies.

Statutory processes: Review design against building regulations. Prepare and submit planning application.

Ensure: Updated cost plan. Signed off stage report by client.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the main outcomes of Stage 4 - Detailed Design?

A

Outcome: All design information required to manufacturer and construct the project completed.

Core tasks: Develop architectural and engineering technical design. Prepare and coordinate design team building system information.

Statutory processes: Submit building regulations application. Discharge any pre-commencement planning conditions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the key outcomes of Stage 5 - Manufacturer and Construction?

A

Outcome: Manufacturing and construction completed.

Core tasks: Construct building. Monitor progress against construction programme. Inspect construction quality.

Statutory processes: Carry out Construction Phase Plan. Comply with planning conditions relating to construction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the key outcomes of Stage 6 - Handover?

A

Outcome: Building handed over, aftercare initiated and building contract concluded.

Core tasks: Hand over building in line with Plan for Use strategy. Undertake review of project performance.

Statutory processes: Comply with planning conditions as required. Building Control sign off.

Ensure: Feedback on project performance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the key outcomes of Stage 7 - Use?

A

Outcome: Building used, operated and maintained efficiently until end of intended lifespan.

Core tasks: Implement facilities management. Undertake post occupancy evaluation of building performance in use.

Statutory processes: Comply with planning conditions as required.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the key parts of Approved Document B relate to designing an office refurbishment?

A

Travel distances need to be less than 18m in one direction or 45m in more than one direction at 45 degrees.

Up to 60 people is 1 escape.
Up to 600 people is 2 escpaes.
More than 600 people is 3 escapes.

A inner room (room within a room) should have sufficient fire detection, vision panels, no more than 30 people capacity.

All escape routes should have 2m minimum head room. Fire corridors to have 30m fire protection.

Fire escape stairs should be between 1000mm and 1800mm depending on the number of floors and occupants.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is an inner room?

A

This is a room by which escape is only possible by passing through another room.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What extra precautions would you take regarding the inner room?

A

People need to be warned if there is a fire in the outer room. Approved Document B suggests this can be achieved with detection in the outer room with an alarm that can be heard or seen in the inner room or a vision panel between the two rooms.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are preliminaries?

A

These are items and costs that are required to complete the project but do not form a specific part of the works.

They provide the description of the project to allow for cost assessment and specify general conditions and requirements for execution. For example: project description, site access and parking.

Examples of preliminary items include: site welfare, scaffolding, provision of temporary services.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are preambles?

A

A preamble is an explanation of a document. Commonly found in contracts, specifications and bills of quantities. It helps with the interpretation of a document. It may include:
1) Description of parties to the contract
2) Description of the competence of parties to a contract. This will include a set of general standards for quality of goods or services required.
3) Tendering procedures
4) Objectives of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the difference between preliminaries and preambles?

A

Preambles are the explanation of the works. These do not form part of the costings. Preliminaries are used to describe the project and allow costing of items that are required to complete the works.

17
Q

What is NBS?

A

National Building Specification. This provides a specification platform.

18
Q

Why would you use NBS?

A

Allows collaboration - others can be invited to edit the document.

Ensures consistent standard and form for all projects.

All statutory standards are kept up to date, such as British Standards

Is the standard specification platform used in the UK. Contractors are used to working with this form of specification.

19
Q

What is NBS Chorus?

A

A cloud based collaborative specification platform. Allows professionals to produce high quality specifications efficiently.

20
Q

What is a schedule of works?

A

A description of the work in list format often used on smaller projects.

21
Q

What supporting documentation could you include within a specification to the contractors?

A

Specialist surveys (structural engineers, drainage surveys, topographical surveys etc).

22
Q

What does the pre-construction information contain?

A

Information that is in the clients possession or which is reasonably obtained by or on behalf of the client, which is relevant to the construction work and is of an appropriate level of detail and proportionate to the risks involved.

It will include:
A) Information on the project
B) Planning and management of the project
C) Health and safety hazards, including design and construction hazards and how they will be addressed.
D) Any information in any existing health and safety file.

23
Q

What did you include include in your detailed design package for the Office Refurbishment?

A

Preliminaries

Specification
- Included items that were durable, sustainable (where possible) and cost effective.

Tender drawings included:
1) Demolition plan
2) Floor and ceiling finishes
3) Proposed plans (details on shower room and partition wall)

Appendices included:
Asbestos R&D survey
Ironmongery schedule
Fire risk assessment

24
Q

Why did you need to liaise with the mechanical and electrical engineers?

A

It was important to review the drawings to ensure all works had been incorporated. Following a review, it was noted builders work for M&E items including holes and chases would need to be included. (radiators required)