2020 Flashcards
Name the Project Stage where this is most likely to
occur - Retentions are partially released for the first time
Practical Completion
Name the Project Stage where this is most likely to
occur - The Architect considers the contract prices submitted by the contractors
Procurement
Name the Project Stage where this is most likely to
occur - Liquidated damages become payable on several occasions
Contract Administration & Observation
Name the Project Stage where this is most likely to
occur - Variation Price Requests are costed
Contract Administration & Observation
Name the Project Stage where this is most likely to
occur - The Client agrees the Architect’s proposed fee
Pre-design
Name the Project Stage where this is most likely to
occur - The architect assists the client to expand and clarify the initial outline brief
Concept and Preliminary Design
Pre-design
Name the Project Stage where this is most likely to
occur - The specification is completed by the consultant team
Detailed design
Name the Project Stage where this is most likely to
occur - The ‘Contractor’s Performance Bond’ is released
At Practical Completion
Name the Project Stage where this is most likely to
occur - A Schedule of payment is prepared by either the Architect or the Quantitiy Surveyor
Contract Administration & Observation
Name the Project Stage where this is most likely to
occur - Door Schedules are produced and double checked
Detailed design
Name the Project Stage where this is most likely to
occur - The latest stage that a Resource Consent application should be made for a project that is not a Permitted Activity under the Auckland Unitary Plan, so that the Client’s risk and expenditure is kept to a minimum
Developed design
Concept design
Name the Project Stage where this is most likely to
occur - Consultants required for the project are identified for the project
Concept and preliminary design
Name the Project Stage where this is most likely to
occur - Minor defects are remedied to the satisfaction of the Architect
Defects Liability Period
Name the Project Stage where this is most likely to
occur - the Architect first considers the approximate amount of documentation that might be required for a project
Pre-design
Name the Project Stage where this is most likely to
occur - An indicative cost for the project is prepared by the Quantity Surveyor to see if the project is viable with respect to costs and brief requirements
Concept and preliminary design
Start of developed design
The Code of Minimum Standards of Ethical Conduct for Architects:
a) Is enforced by NZRAB, the NZ Registered Architects’ Board
b) Is enforced by MBIE, Ministry of Business, Innovation and Employment
c) Is enforced by NZIA, the NZ Institute of Architects
d) Is enforced by both the NZIA and NZRAB
a) Is enforced by NZRAB, the NZ Registered Architects’ Board
The NZIA is responsible for:
a) Setting up the NZ Registered Architects Board
b) The disciplining Architects
c) The registration of Architects
d) Providing support to architects in practice
d) Providing support to architects in practice
What New Zealand legislation protects the titles of ‘Architect’ and ‘Registered Architect’?
a) The Architects Act 2005
b) The Registered Architects Act 2005
c) The Registered Architects’ Rules 2006
d) The Registered Architects Act 2006
b) The Registered Architects Act 2005
The NZRAB is responsible for:
a) Writing the Architects’ Act
b) The registration of Architects and writing the Architects’ Act
c) The registration of Architects
d) Providing support documents to Architects
c) The registration of Architects
To register as an architect in New Zealand, an applicant needs to have
completed which of the following as a minimum:
a) Be competent across all the experience areas
b) Be competent across all the experience areas and hold a recognised qualification such as MArch (Prof) degree
c) Be competent across all the experience areas and hold a recognised qualification such as MArch (Prof) degree and have completed 480
hours minimum practical experience
d) Be competent across all the experience areas and hold a recognised qualification such as MArch (Prof) degree and have completed 5,250 hours minimum practical experience
d) Be competent across all the experience areas and hold a recognised qualification such as MArch (Prof) degree and have completed 5,250 hours minimum practical experience
Where is it specifically written that an Architect must have their terms of appointment recorded in writing, agreed to, and a formal instruction to proceed issued by the client?
a) In the Code of Minimum Standards of Ethical Conduct for Architects
b) On the NZIA website
c) On the NZIA website and in the Registered Architects Act
d) In the Registered Architects’ Act
a) In the Code of Minimum Standards of Ethical Conduct for Architects
Which of the following consultants are most usually employed as separate consultants as opposed to sub-consultants?
a) The Architect
b) The Quantity Surveyor
c) The Architect and the Quantity Surveyor
d) The Architect, Quantity Surveyor and the contractor
c) The Architect and the Quantity Surveyor
An Architect running a small design firm requires which of the following
management skills:
a) Practice and project management
b) Practice, project and human resources management
c) Project, financial and human resources management
d) Practice, project, financial and human resources management
d) Practice, project, financial and human resources management
The most common forms of architectural practice in New Zealand are:
a) Sole practitioners, partnerships and companies
b) Sole practitioners and limited liability companies
c) Sole practitioners and companies
d) Sole practitioners, limited liability companies and partnerships
b) Sole practitioners and limited liability companies
PI (Professional Indemnity) Insurance:
a) Is held by the Contractor, as required under NZIA SCC
b) Is held by the Client, as required by the NZIA AAS
c) Is held by the Architect, as required by the NZRAB
d) Is held by the Architect, as required by the NZRAB and required of the
Contractor if they are undertaking any design work
d) Is held by the Architect, as required by the NZRAB and required of the Contractor if they are undertaking any design work
A separate Contractor is engaged and paid for by:
a) The Principal
b) The Architect
c) The Contractor
d) The Quantity Surveyor
a) The Principal
The standard position in New Zealand for copyright ownership of the Architect’s drawings is:
a) The Architect always holds the copyright
b) The Client holds the copyright once they have paid the Architect
c) The Client holds the copyright irrespective of payment, unless a separate agreement is entered into
d) The Architect and the Client hold joint copyright
c) The Client holds the copyright irrespective of payment, unless a separate agreement is entered into
Which of the following statements relating to the charging of fees is the most correct?
a) Time charges are best used where required services are of an unknown
extent and duration
b) Lump sum fees are best used where services are of an unknown extent
and duration
c) Time charge fees are best used where services are of a known extent
and duration
d) Percentage fees are best used where the client is a developer
a) Time charges are best used where required services are of an unknown extent and duration