2018 Flashcards
During which Project Stage does this occur?
The Architect proposes a fee for their services to the Client
Pre-design
During which Project Stage does this occur?
The contractor proposes a cost or contract sum to the client to carry out the contract works
Procurement
During which Project Stage does this occur?
The contractor completes agreed deferred works and minor errors
Defects Liability Period
During which Project Stage does this occur?
Tenders are evaluated by the Architect
Procurement
During which Project Stage does this occur?
A topographical survey is undertaken by a registered land surveyor
Pre-design
During which Project Stage does this occur?
The client takes over contract insurances from the contractor for a new building
Practical Completion
During which Project Stage does this occur?
Construction documentation is finalised by the Architect for Building Consent
Detailed Design
During which Project Stage does this occur?
Liquidated Damages are first charged to the contractor where the project has not been completed according to the agreed programme
Contract Admin & Observation
During which Project Stage does this occur?
The specification is completed by the architect
Detailed Design
During which Project Stage does this occur?
Consultants’ requirements are first incorporated into the design prior to their full coordination
Concept & Preliminary Design
Where would one look to find the most up to date Development Controls for Auckland?
a) The Building Act
b) The District Plan
c) The Auckland Unitary Plan
d) The Resource Management Act
c) The Auckland Unitary Plan
A Topographical Surveyor:
a) provides legal information of the land
b) provides levels of the site
c) provides sub-soil information
d) provides Schedules of Quantities
b) provides levels of the site
Where can one read the Code of Minimum Standards of Ethical Conduct for Architects?
a) On the NZIA website and written within the Registered Architect’s Rules
b) On the NZRAB website and written within the Registered Architect’s Rules
c) On the NZRAB website
d) Written within the Registered Architect’s Rules
b) On the NZRAB website and written within the Registered Architect’s Rules
The ‘Architect’ named within the NZIA SCC document:
a) Is automatically the Architect’s representative
b) Is a director of the Architectural practice
c) Is automatically the Project Architect for the job
d) Is the name of the architectural practice
d) Is the name of the architectural practice
The most accurate estimates for building costs at the Developed Design stage of a project are produced by:
a) The Quantity Surveyor
b) The Cadastral Surveyor
c) The Architect
d) The Contractor
a) The Quantity Surveyor
P and G means:
a) The profit and general that the principal pays for the project
b) The profit and general that the contractor pays for the project
c) The preliminaries and general that the contractor pays for the project
d) The preliminaries and general that the principal pays for the project
c) The preliminaries and general that the contractor pays for the project
Which of the following consultants are most usually employed as separate consultants as opposed to sub-consultants?
a) The Architect
b) The Architect and the Quantity Surveyor
c) The Architect, Quantity Surveyor and the contractor
d) The Quantity Surveyor
b) The Architect and the Quantity Surveyor
Who usually employs the sub-contractors on a project?
a) The Contractor
b) The Client
c) The Project Manager
d) The Architect
a) The Contractor
Which of the following statements relating to the charging of fees is the most correct?
a) Time charges are used where required services are of an unknown extent and duration
b) Lump sum fees are used where services are of an unknown extent and duration
c) Time charge fees are used where services are of a known extent and duration
d) Percentage fees are used where the client is a developer
a) Time charges are used where required services are of an unknown extent and duration
Which organisation is responsible for writing the ethical standards that Registered Architects are bound by?
a) The NZIA
b) The NZRAB
c) The NZIA & NZRAB
d) The MBIE
b) The NZRAB