2019 Flashcards
Which Project Stage is this most likely to
occur - A ‘Variation’ to the contract is issued
Contract Administration and Observation
Which Project Stage is this most likely to
occur - A geotechnical survey is instructed for establishing the nature of the land beneath the proposed building footprint
Concept & Preliminary Design
Which Project Stage is this most likely to
occur - A ‘Bonus for Early Completion’ of the project is paid out
At Practical Completion or start of Defects Liability Period
Which Project Stage is this most likely to
occur - The last stage where the amount of contract works insurance required for the project can be established
Start of Procurement; end of Detailed Design
Which Project Stage is this most likely to
occur - The ‘Principal’s Bond’ is released
Final account
Which Project Stage is this most likely to
occur - The Client presents their design brief to the Architect for the first time
Pre-design
Which Project Stage is this most likely to
occur - The earliest stage that a Resource Consent application can be made to establish the likelihood of consent success for a project typology that is not a Permitted activity under the Auckland Unitary Plan and to minimise the Client’s financial input into a project that may not proceed
Concept & Preliminary Design
Which Project Stage is this most likely to
occur - Minor defects are remedied to the satisfaction of the Architect
Defects Liability Period
Which Project Stage is this most likely to occur - The Quantity Surveyor can establish a reasonably accurate and comprehensive cost plan for the proposed project, incorporating all of the Consultants’ design requirements to meet the Client’s brief
Detailed Design
Which Project Stage is this most likely to
occur - The Contractor issues a ‘Progress Payment’ claim
Contract Administration and Observation
The NZIA is responsible for:
a) Providing support to architects in practice
b) The registration of Architects
c) Disciplining Architects
d) Setting up the NZ Registered Architects Board
a) Providing support to architects in practice
A Quantity Surveyor:
a) Can provide site legal information
b) Can provide site levels
c) Can provide site sub-soil information
d) Can provide a schedule to assist contractors to cost a project
d) Can provide a schedule to assist contractors to cost a project
The titles of ‘Architect’ and ‘Registered Architect’ are protected under what legislation?
a) The Architects Act 2005
b) The Registered Architects Act 2005
c) The Registered Architects’ Rules 2006
d) The Code of Minimum Standards of Ethical Conduct for Architects
b) The Registered Architects Act 2005
‘General’ is a term that refers to:
a) General costs for all of the project costs
b) All the project establishment costs that are not actual building costs
c) General time frames for the project
d) The Contractor’s profit margin
b) All the project establishment costs that are not actual building costs
Where a project’s duration and extent of work is known in advance, the client is likely to accept the Architect’s fee charging methodology as:
a) A time charge fee
b) A lump sum fee with additional works as a percentage fee
c) A percentage fee with additional works as a lump sum fee
d) A percentage or lump sum fee with additional works as a time charge fee
d) A percentage or lump sum fee with additional works as a time charge fee
Where is it specifically written that an Architect must have their terms of appointment recorded in writing, agreed to, and a formal instruction to proceed issued by the client?
a) In the Code of Minimum Standards of Ethical Conduct for Architects
b) On the NZIA website
c) On the NZIA website and in the Registered Architects Act
d) In the Registered Architects’ Act
a) In the Code of Minimum Standards of Ethical Conduct for Architects
A separate Contractor is engaged and paid for by:
a) The Principal
b) The Architect
c) The Contractor
d) The Quantity Surveyor
a) The Principal
To successfully manage an architectural practice, which of the following management skills are necessary?
a) Practice and financial management skills
b) Project, human resources and practice management skills
c) Project, human resources, financial and practice management skills
d) Practice, human resources and financial management skills
c) Project, human resources, financial and practice management skills
To become registered as an Architect in New Zealand, which of the following conditions need to be met?
a) Adequate practical work experience
b) A recognised architectural degree and a minimum length of practical work experience
c) A recognised architectural degree and adequate practical work experience that is equal to or more than the minimum experience length requirement
d) A recognised architectural degree, adequate practical work experience that is equal to or more than the minimum experience length requirement and evidence of competency in all of the experience areas
d) A recognised architectural degree, adequate practical work experience that is equal to or more than the minimum experience length requirement and evidence of competency in all of the experience areas
Which of the following are the most common typologies available today for New Zealand Architects to structure their architectural practices?
a) Partnerships and companies
b) Sole practitioners and limited liability companies
c) Sole practitioners and companies
d) Sole practitioners, limited liability companies and partnerships
b) Sole practitioners and limited liability companies