1532 Contract Disputes & Appeals Flashcards

1
Q

A written demand or written assertion by one of the contracting parties seeking, as a matter of right, the payment of money in a sum certain, the adjustment or interpretation of contract terms, or other relief arising under or relating to the contract

A

Claim, Must be certified

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The date when all events, that fix the alleged liability of either the Government or the contractor and permit assertion of the claim, were known or should have been known

A

Accrual of a claim

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Any type of procedure or combination of procedures voluntarily used to resolve issues in controversy

A

Alternative Dispute Resolution

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

A certificate which alters or otherwise deviates from the language in 33.207(c) or which is not executed by a person duly authorized to bind the contractor with respect to the claim.

A

Defective Certification

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

A material disagreement between the Government and the contractor that may result in a claim and Is all or part of an existing claim

A

Issue in controversy

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

A false statement of substantive fact, or any conduct which leads to the belief of a substantive fact material to proper understanding of the matter in hand, made with intent to deceive or mislead

A

Misrepresentation of fact

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What Act Establishes procedures and requirements for asserting and resolving claims and provides for, Payment of interest on contractor claims, Certification of contractor claims and Civil penalty for contractor claims that are fraudulent or based on a misrepresentation of fact

A

Contract Disputes Act of 1978

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Contractor’s have _______ to file a claim unless the parties agree to a shorter time period

A

6 years

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

After review of the claim and all associated facts to include legal review, the contracting officer has _____ to issue a final decision.

A

60 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Any claim exceeding _____________ shall be certified in writing by the contractor

A

$100,000

How well did you know this?
1
Not at all
2
3
4
5
Perfectly