L7 Flashcards
What does PERT technique stand for?
Performance Evaluation Review Technique
What types of questions can we answer with PERT?
- what’s the probability of it being done in X days
- what’s the completion time, guaranteed with a 95% probability?
What does PERT assume?
- the critical path is always the critical path
- activities are statistically independent
- variance of activities is the sum of the individual variances
- project duration is normal distribution
What is the standard deviation equation?
Square root of variance
What’s the standard deviation equation for the path?
Square root (sum of variances of activities on the path)
What is the variance of the completion time?
The sum of the variances on the critical path.
What is the expected time to completion?
The sum of expected time on the critical path.
Why is the standard deviation equation divided by 6?
Because if you take the tails of the normal distribution (pessimistic, optimistic), they will be 6 sds apart.
What is more typically used than PERT in practice?
Simulation software:
- Crystal Ball
- @risk
Overkill if time is low priority
Defo use if time is important
Limitations of CPA and Gantt charts?
- durations are hard to estimate
- doesn’t handle resource constraints
- may cause excessive multi-tasking
- complex for large projects
Why are project duration/cost estimates so often wrong?
- Duration estimates are often given large safety margins.
- Parkinson’s Law says that task durations expand to fill the time available.
- early finish is disadvantageous (new work etc)
- extra time used to polish the result
- Student syndrome: tasks aren’t started early
- Murphys Law: the unexpected will happen
- Time/quality is lost switching between tasks
What is a way of mitigating against the estimation problems with CPA?
Use critical chain buffer management.
What does critical chain buffer management involve? CCBM
- don’t add safety margins
- mitigates against Parkinson’s law/student syndrome
- remove stigma of late finish
- ask for median time
What is a critical chain?
The sequence of precedence and resource dependent elements that prevent projects being completed in less time, given available resources.
What’s the difference between critical path and critical chain?
Critical chain also focuses on resources.
If resources were unlimited, they would be the same.
We add a buffer to CCBM.