L7 Flashcards

1
Q

What does PERT technique stand for?

A

Performance Evaluation Review Technique

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What types of questions can we answer with PERT?

A
  • what’s the probability of it being done in X days
  • what’s the completion time, guaranteed with a 95% probability?
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What does PERT assume?

A
  • the critical path is always the critical path
  • activities are statistically independent
  • variance of activities is the sum of the individual variances
  • project duration is normal distribution
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the standard deviation equation?

A

Square root of variance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What’s the standard deviation equation for the path?

A

Square root (sum of variances of activities on the path)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the variance of the completion time?

A

The sum of the variances on the critical path.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the expected time to completion?

A

The sum of expected time on the critical path.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Why is the standard deviation equation divided by 6?

A

Because if you take the tails of the normal distribution (pessimistic, optimistic), they will be 6 sds apart.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is more typically used than PERT in practice?

A

Simulation software:
- Crystal Ball
- @risk

Overkill if time is low priority
Defo use if time is important

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Limitations of CPA and Gantt charts?

A
  • durations are hard to estimate
  • doesn’t handle resource constraints
  • may cause excessive multi-tasking
  • complex for large projects
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Why are project duration/cost estimates so often wrong?

A
  1. Duration estimates are often given large safety margins.
  2. Parkinson’s Law says that task durations expand to fill the time available.
  • early finish is disadvantageous (new work etc)
  • extra time used to polish the result
  1. Student syndrome: tasks aren’t started early
  2. Murphys Law: the unexpected will happen
  3. Time/quality is lost switching between tasks
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is a way of mitigating against the estimation problems with CPA?

A

Use critical chain buffer management.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What does critical chain buffer management involve? CCBM

A
  • don’t add safety margins
  • mitigates against Parkinson’s law/student syndrome
  • remove stigma of late finish
  • ask for median time
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is a critical chain?

A

The sequence of precedence and resource dependent elements that prevent projects being completed in less time, given available resources.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What’s the difference between critical path and critical chain?

A

Critical chain also focuses on resources.

If resources were unlimited, they would be the same.

We add a buffer to CCBM.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are the 3 buffers in CCBM?

A

Project buffer: insert at end of proj.

Feeding buffer: insert at end of task paths feeding critical chain.

Resource buffer: insert when non-critical task precedes a critical one and both share a common resource.

17
Q

What’s the suggested buffer size in CCBM?

A

50%

Any extra days between what you ask the client for eg 23 days and how long it’ll take eg 21 days.

18
Q

Steps in CCBM:

A
  1. Estimate task durations
  2. Determine the projects critical chain(s)
  3. Include buffers to protect critical chain
  4. Project control
  5. Resource allocation
19
Q

What is involved in project control in CCBM compared to traditional?

A
  • traditional: due dates, task completion %
  • But with CCBM: monitor state of buffers (and rate at which they deplete)
20
Q

How do you approach resource allocation in CCBM?

A

Schedule tasks with limited resources first.

21
Q

What are some inevitable problems even with CCBM?

A
  • errors
  • oversight
  • staff over commitments
  • bottlenecks
  • imbalances in workload
  • slack time is wasted