1206.0 Standpipe / Sprinkler Operations Flashcards
1
Q
II. Pumping Pressure:
A. Engine pressure equals: 1. \_\_\_\_\_ PSI at the Fire Department Connection (FDC), PLUS 2. \_\_\_\_ PSI per floor of elevation, beginning with the second floor.
A
150 / 5
2
Q
II. Pumping Pressure:
B. Friction loss in the \_\_\_\_\_\_\_\_ \_\_\_\_\_\_ is a minimal number and need not be calculated into the above formula.
A
supply line
3
Q
II. Pumping Pressure:
C. Example: Standpipe or sprinkler is activated on the fifth floor. 5" Supply Line \_\_\_\_\_ PSI at the FDC \_\_\_\_ PSI for elevation \_\_\_\_\_ PSI = Engine Pressure
A
150 / 20 / 170
4
Q
II. Pumping Pressure:
D. The engine pressure shall not exceed the \_\_\_\_ PSI test pressure of the 5" hose.
A
200
5
Q
III. FDC Procedure:
A. Reverse lay a 5" supply line from the? The FDC end will require the use of the 5" \_\_\_\_\_ to \_\_\_\_\_ \_\_\_\_\_\_ adapter. Break the 5" supply line and attach it to the 5" \_\_\_\_\_\_\_\_ \_\_\_\_\_\_\_ of the pump. B. Utilizing the 50' section of 5" supply line on the left side of the engine, complete the hydrant connection to the?
A
FDC to an appropriate hydrant
5” Storz to 2 1/2 male adapter
discharge outlet
Piston Intake Relief Valve (PIRV)
6
Q
I. High Rise Hose Load:
A. One of the \_\_\_\_\_\_ \_\_\_\_\_\_\_ shall be utilized as the high rise load. B. The hose shall be advanced using the \_\_\_\_\_\_\_\_\_ \_\_\_\_\_\_\_\_ carry method.
A
Dead Loads / accordion shoulder