10-Construction Phase-Office Functions Flashcards

1
Q

In a CCDC 2 contract, which of the following is responsible for the preparation of a change directive?*

A) Architect
B) Building Inspector
C) General Contractor
D) Owner

A

A) Architect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

In CCDC2 who is responsible for issuing progress claims?

A

The contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Who determine the construction methods, building sequence and techniques?

A

The contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

True or false? The architect must approve all change orders before the contractor can execute.

A

False. The Owner must approve the change order. A change order changes the contract price. The architect and other consultant can review/comment the cost before seeking the owner’s approval

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

True or false? The architect apply for the certificate of substantial completion.

A

False! The contractor does

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Who provide the letter of Assurance?

A

The architect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How long is the standard warranty of a project?

A

1-year

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the documentation required of the contractor prior to the mobilisation of construction? (10)

A
  • Contract, signed
  • Bond
  • Labour & Material bond
  • Performance bond
  • Insurance certificate
  • Property insurance
  • Building Permit from the AHJ
  • Proof of current standing with the provincial or territorial Health & Safety authority
  • Job site accident prevention
  • Confirm waste management plan
  • Hazardous materials assessment if applicable
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is a holdback, what is the typical % of holdback?

A

A percentage of the monetary amount payable under a (construction) contract, which is held as security for a certain period. The percentage and period are based on the provincial lien legislation.

10%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is substantial performance? Name a synonym

A

Ready-to-take-over (substantial performance): describe a set of conditions that must be fulfilled to consider the contractual obligation completed and resulting in the release of the close-out payment (i.e. release of holdback)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

True or false. Commissioning is part of the basic services

A

False, it is an additional service

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is commissioning?

A

Systematic process of ensuring that new building systems perform according to the design intent and the owner’s operational needs, that all system documentations are provided and the training is provided to the facility staff.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is in a contract summary in a change order.

A

Original contract price
Value of change order issued
Current value of change directives
Value of contract of last day of the payment period
Total amount payable including value added taxes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

3 tasks for Arch. to perform prior to construction phase (but after bid award)

A

1 • prep 2 copies of original contracts for signature and seal by contractor and client/owner (note: also make 1 copy without seals for Arch. to keep)

2 • preps/shares updated drawings, consolidating all changes to date (addenda etc.) on one issue for construction (IFC) set

3 • check CDs against documents submitted by GC to ensure compliance, particularly items listed in spec sections: General Conditions & Supplemental Conditions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

4 distinct stages of Construction Administration:

A

1 - Prior to Construction

2 - During Construction

3 - Close-Out

4 - Warranty Period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Role of Client during CA: (4)

A
  • provide finance information
  • make payments to contractor
  • authorize changes in work
  • provide prompt decisions & directions
17
Q

1 - Is Commissioning part of the basic architectural fee?
2 - Do Architects typically include this in their scope of services?

A

1 - Yes

2 - Commissioning is typically executed by an independent third party, as quality assureance for the client/owner

18
Q

define the 3 types of occupancy

A

1 - “Unconditional” Scope of work, as outlined by BP, is complete and deemed compliant by AHJ

2 - “Conditional” Full scope of work is not complete, but current progress deemed ‘safe’ by AHJ

3 - “Phased” or “Partial” A portion of the scope is complete and deemed compliant with BP by AHJ

19
Q

What are the 5 stages of final completion and take-over for construction projects.

A
  1. GC inspection for Substantial Performance
  2. GCs app. for Cert. of Sub. Performance
    inc: statement, cost values of (in)complete work, data (manuals record dwgs, etc)
    O/A/Eng must inspect within 10 days and confirm or deny within 7 days of inspect.
  3. Following Sub. Perf.
    holdback payable to GC on the first day after lien expiry period, which begins on date of issuance of Certificate of Substantial Performance.
  4. Application for Final Payment
    Final Inspection
    O/A/Eng prep Deficiency List
    GC to correct any deficiencies they can
  5. Guarantee Period
    inspection no later than 10 days befor expiry of guarantee period
    O/A/Eng prep Final Deficiency List
20
Q

What is the GC’s role in reviewing shop drawings?

A

Confirm:

  1. Quantities
  2. Dims
  3. Accuracy
  4. Completeness
  5. Compliance w Spec
21
Q

What does commissioning ensure and when does it begin?

A

An integrated system which functions according to client intent. This process can begin at the start of the project, by setting out a functional program and design intent for the client/owner.

22
Q

What are the 2 lists that must be prepared by the GC and reviewed by O / A / Eng within 14 days of receipt?

A

by O / A / Eng within 14 days of receipt?

  1. ITEMS RQD FOR OPERATION OF OCCUPIED PREMISES:
    • data
    • operating instructions
    • spare parts
    • materials
    • etc
  2. ITEMS RQD TO COMPLETE CONTRACT / RELEASE CERT PAYMENT:
    • stat dec
    • WCB (good standing)
    • Guarantees
    • etc. (as rqd by CDs)