08-Quality Management Flashcards
1
Q
1. When a product or service completely meets a customer's requirements: A. Quality is achieved. B. The cost of quality is high. C. The cost of quality is low. D. The customer pays the minimum price.
A
- Answer A
Explanation As a general rule, one cannot say that quality (as defined in the question) is either of high or low cost. It provides what the customer wanted, which may not be the lowest or highest cost. When a product or service completely meets a customer’s needs, quality is achieved.
2
Q
2. To what does the following definition refer? "The point where the benefits or revenue to be received from improving quality equals the incremental cost to achieve that quality!' A. Quality control analysis B. Marginal analysis C. Standard quality analysis D. Conformance analysis
A
- Answer B
Explanation This is the definition of marginal analysis. Know the term so you will be able to answer questions that deal with this concept. The other choices may sound good, but they are made-up terms.
3
Q
3. Who is ultimately responsible for quality management on the project? A. The project engineer B. The project manager C. The quality manager D. The team member
A
- Answer B
Explanation Although each person working on the project should check his or her own work, the
project manager ultimately has the responsibility for quality on the project as a whole.
4
Q
- A project has faced major difficulties in the quality of its deliverables. Management now states that quality is the most important project constraint. If another problem with quality were to occur, what would be the BEST thing for the project manager to do?
A. Fix the problem as soon as possible.
B. Allow the schedule to slip by cutting cost.
C. Allow cost to increase by fixing the root cause of the problem.
D. Allow risk to increase by cutting cost.
A
- Answer C
Explanation If a problem with quality were to occur again, many people would opt to fix the problem as soon as possible. It is proactive, but some other project constraint(s) must change to accommodate fixing the root cause of the problem. It may not be necessary to allow the schedule to slip, because the project manager might be able to compress the schedule in other areas. Cutting cost does not necessarily cause the schedule to slip, nor would that necessarily fix the problem at hand. Allowing risk to increase by cutting cost is not the best choice, because a quality problem is most likely to create additional cost, rather than cut cost. Allowing the cost to increase by fixing the root cause of the problem addresses both finding the cause and the probable impact of dealing with the problem.
5
Q
- A manager notices that a project manager is holding a meeting with some of the team and some stakeholders to discuss the quality of the project. The project schedule has been compressed, and the CPI is 1.1. They have worked hard on the project, the team has been rewarded according to the reward system the project manager put in place, and there is a strong sense of team. The manager suggests that the project manager does not have enough time to hold meetings about quality when the schedule is so compressed. Which of the following BEST describes why the manager is wrong?
A. Improved quality leads to increased productivity, increased cost effectiveness, and decreased cost risk.
B. Improved quality leads to increased productivity, decreased cost effectiveness, and increased cost risk.
C. Improved quality leads to increased productivity, increased cost effectiveness, and increased cost risk.
D. Improved quality leads to increased productivity, decreased cost effectiveness, and decreased cost risk.
A
- Answer A
Explanation Did you notice there is a lot of data not relevant to answering the question? Expect distracters to appear in many questions on the exam. Quality efforts should produce a decrease rather than an increase in cost risk as a result of less rework. Quality efforts should also provide increased cost effectiveness due to less rework. This leaves the best answer: “Improved quality leads to increased productivity, increased cost effectiveness, and decreased cost risk:’
6
Q
- Quality is:
A. Meeting and exceeding the customer’s expectations.
B. Adding extras to make the customer happy.
C. The degree to which the project meets requirements.
D. Conformance to management’s objectives.
A
- Answer C
Explanation There can be a cost impact (or time, risk, etc.) of exceeding expectations or adding extras. Quality is the degree to which the project meets requirements.
7
Q
7. All the following are tools of Control Quality EXCEPT: A. Inspection. B. Cost of quality. C. Pareto diagram. D. Fishbone diagram.
A
- Answer B
Explanation Inspection, Pareto diagrams, and fishbone diagrams are all tools that can be used in Control Quality. Cost of quality is part of Plan Quality Management, making sure the project is not spending too much to achieve a particular level of quality
8
Q
- Pareto diagrams help the project manager:
A. Focus on the most critical issues to improve quality.
B. Focus on stimulating thinking.
C. Explore a desired future outcome.
D. Determine if a process is out of control.
A
- Answer A
Explanation Fishbone diagrams are often used to stimulate thinking and to explore a desired future outcome. Determining whether a process is out of control is a function of control charts. Only focusing on critical issues to improve quality relates to Pareto diagrams.
9
Q
- A control chart helps the project manager:
A. Focus on the most critical issues to improve quality.
B. Focus on stimulating thinking.
C. Explore a desired future outcome.
D. Determine if a process is functioning within set limits.
A
- Answer D
Explanation Focusing on the most critical issues to improve quality relates to Pareto diagrams. Stimulating thinking and exploring a desired future outcome relate to fishbone diagrams. Only determining if a process is functioning within set limits relates to control charts.
10
Q
10. Testing the entire population would: A. Take too long. B. Provide more information than wanted. C. Be mutually exclusive. D. Show many defects.
A
- Answer A
Explanation The length of time it takes to test a whole population is one of the reasons to take a sample.
11
Q
11. All of the following are examples of the cost of nonconformance EXCEPT: A. Rework. B. Quality training. C. Scrap. D. Warranty costs.
A
- Answer B
Explanation Quality training is a cost of conformance to quality. All the other choices are costs of nonconformance to quality.
12
Q
- Standard deviation is a measure of how:
A. Far the estimate is from the highest estimate.
B. Far the measurement is from the mean.
C. Correct the sample is.
D. Much time remains in the project.
A
- Answer
Explanation Standard deviation is the measurement of a range around the mean.
13
Q
- All of the following result from quality audits EXCEPT:
A. Determination of whether project activities comply with organizational policies.
B. Improved processes to increase productivity.
C. Creation of quality metrics.
D. Confirmation of the implementation of approved change requests.
A
- Answer C
Explanation Quality metrics are an output of the Plan Quality Management process. They are an input to the Perform Quality Assurance process, the process in which quality audits take place.
14
Q
- A control chart shows seven data points in a row on one side of the mean. What should be done?
A. Perform a design of experiments.
B. Adjust the chart to reflect the new mean.
C. Find an assignable cause.
D. Nothing. This is the rule of seven and can be ignored.
A
- Answer C
Explanation The rule of seven applies here. If you have seven data points in a row on the same side of the mean, statistically the mean has shifted, calling for action to correct the problem.
15
Q
15. You are managing a project in a just in time environment. This will require more attention, because the amount of inventory in such an environment is generally: A. 45 percent. B. 10 percent. C. 12 percent. D. 0 percent.
A
- Answer D
Explanation In a just in time environment, supplies are delivered when you need them and not before. Therefore, you have little or no inventory.
16
Q
- There are several executing activities underway on your project. You are beginning to get
concerned about the accuracy of the progress reporting your team members are doing. How could you verify whether there is a problem?
A. Quality audits
B. Risk quantification reports
C. Regression analysis
D. Monte Carlo analysis
A
- Answer A
Explanation Quality audits are a necessary part of the Perform Quality Assurance process. They help you assess whether the processes are being followed correctly on the project.