05-Scope Management Flashcards
1
Q
- A work breakdown structure numbering system allows the project team to:
A. Systematically estimate costs of work breakdown structure elements.
B. Provide project justification.
C. Identify the level at which individual elements are found.
D. Use it in project management software.
A
- Answer C
Explanation The numbering system allows team members to quickly identify the level in the work breakdown structure where the specific element is found. It also helps to locate the element in the WBS dictionary.
2
Q
2. The work breakdown structure can BEST be thought of as an effective aid for communications. A. Team B. Project manager C. Customer D. Stakeholder
A
- Answer D
Explanation The term “stakeholder” encompasses all the other choices. In this case, it is the best answer since the WBS can be used (but does not need to be used) as a communications tool for all stakeholders to “see” what is included in the project.
3
Q
- Which of the following is a KEY output of the Validate Scope process?
A. A more complete scope management plan
B. Customer acceptance of project deliverables
C. Improved schedule estimates
D. An improved project management information system
A
- Answer B
Explanation The output of the Validate Scope process is customer acceptance of project deliverables. The other choices all happen during project planning, well before the time the Validate Scope process takes place.
4
Q
4. During project executing, a team member comes to the project manager because he is not sure what work he needs to accomplish on the project. Which of the following documents contains detailed descriptions of work packages? A. WBS dictionary B. Activity list C. Project scope statement D. Scope management plan
A
- Answer A
Explanation Activity lists may identify the work package they relate to, but they do not contain detailed descriptions of the work packages. The project scope statement defines the project scope, but it does not describe the work a team member is assigned. The scope management plan describes how scope will be planned, managed, and controlled. It does not include a description of each work package. The WBS dictionary defines each element in the WBS. Therefore, descriptions of the work packages are in the WBS dictionary.
5
Q
5. During which part of the project management process is the project scope statement created? A. Initiating B. Planning C. Executing D. Monitoring and controlling
A
- Answer B
Explanation The project scope statement is an output of the Define Scope process, which occurs during project planning.
6
Q
6. The program was planned years ago, before there was a massive introduction of new technology. While planning the next project in this program, the project manager has expanded the scope management plan because, as a project becomes more complex, the level of uncertainty in the scope: A. Remains the same. B. Decreases. C. Decreases then increases. D. Increases.
A
- Answer D
Explanation Not all questions will be difficult. The level of uncertainty in scope increases based on the scale of effort required to identify all the scope. For larger projects, it is more difficult to “catch” everything.
7
Q
- During a meeting with some of the project stakeholders, the project manager is asked to add work to the project scope. The project manager had access to correspondence about the project before the project charter was signed and remembers that the project sponsor specifically denied funding for the scope mentioned by these stakeholders. The BEST thing for the project manager to do is to:
A. Let the sponsor know of the stakeholders’ request.
B. Evaluate the impact of adding the scope.
C. Tell the stakeholders the scope cannot be added.
D. Add the work if there is time available in the project schedule.
A
- Answer C
Explanation Although one could let the sponsor know about the stakeholders’ request, the best choice listed would be to say no, as this was already considered. An even better choice would be to find the root cause of the problem, but that choice is not listed here.
8
Q
- A new project manager is being mentored by a more experienced PMP-certified project manager. The new project manager is having difficulty finding enough time to manage the project because the project scope is being progressively elaborated. The PMP-certified project manager advises that the basic tools for project management, such as a work breakdown structure, can be used during project executing to assist the project manager. For which of the following can a work breakdown structure be used?
A. Communicating with the customer
B. Showing calendar dates for each work package
C. Showing the functional managers for each team member
D. Showing the business need for the project
A
- Answer A
Explanation A WBS does not show dates or responsibility assignments. The business need is described in the project charter. In this situation, the project scope is being fine-tuned. It would save the project manager time in effectively managing progressive elaboration if the Vv’liS was used as a communications tool. Using the WBS helps ensure everyone (including the customer) understands the scope of the work.
9
Q
9. During a project team meeting, a team member suggests an enhancement to the scope that is beyond the scope of the project charter. The project manager points out that the team needs to concentrate on completing all the work and only the work required. This is an example of: A. Change management process. B. Scope management. C. Quality analysis. D. Scope decomposition.
A
- Answer B
Explanation The team member is suggesting an enhancement that is outside the scope of the project charter. Scope management involves focusing on doing the work and only the work in the project management plan that meets the objectives of the project charter. The project manager is performing scope management.
10
Q
- When should the Validate Scope process be done?
A. At the end of the project
B. At the beginning of the project
C. At the end of each phase of the project
D. During the planning processes
A
- Answer C
Explanation The Validate Scope process occurs during project monitoring and controlling. It is done at the end of each project phase to get approval for phase deliverables, as well as at other points to get approval for interim deliverables.
11
Q
- The project is mostly complete. The project has a schedule variance of 300 and a cost variance of -900. All but one of the quality control inspections have been completed and all have met the quality requirements. All items in the issue log have been resolved. Many of the resources have been released. The sponsor is about to call a meeting to obtain product validation when the customer notifies the project manager that they want to make a major change to the scope. The project manager should:
A. Meet with the project team to determine if this change can be made.
B. Ask the customer for a description of the change.
C. Explain that the change cannot he made at this point in the process.
D. Inform management.
A
- Answer B
Explanation Do not jump into the problem without thinking. The customer only notified the project manager that they want to make a change. They did not describe the change. The project manager should not say no until he or she knows more about the potential change, nor should the project manager go to management without more information. The project manager must understand the nature of the change and have time to evaluate the impact of that change before doing anything else. Of these choices, the first thing to do is to determine what the change is. The project manager might then analyze the potential change with the team, but only if their input is required.
12
Q
- You have just joined the project management office after five years of working on projects. One of the things you want to introduce to your company is the value of creating and utilizing work breakdown structures. Some of the project managers are angry that you are asking them to do “extra work.” Which of the following would be the BEST thing you could tell the project managers to convince them to use work breakdown structures?
A. Work breakdown structures will prevent work from slipping through the cracks.
B. Work breakdown structures are only needed on large projects.
C. Work breakdown structures are required only if the project involves contracts.
D. Work breakdown structures are the only way to identify risks.
A
- Answer A
Explanation Work breakdown structures are required on projects of every size, regardless of whether contracts are involved. Work breakdown structures can be used to help identify risks, but risks can be identified using other methods as well. Preventing work from being forgotten (slipping through the cracks) is one of the main reasons the tool is used, and is the best choice offered here.
13
Q
13. A new project manager has asked you for advice on creating a work breakdown structure. After you explain the process to her, she asks you what software she should use to create the WBS and what she should do with it when it is completed. You might respond that it is not the picture that is the most valuable result of creating a WBS. The most valuable result of a WBS is: A. A bar chart. B. Team buy-in. C. Activities. D. A list of risks.
A
- Answer B
Explanation The WBS is an input to all of these choices. However, team buy-in is a direct result of the WBS creation process, while the other choices use the WBS to assist in their completion. Involving the team in creating the WBS provides project team members with an understanding of where their pieces fit into the overall project management plan and gives them an indication of the impact of their work on the project as a whole.
14
Q
- To manage a project effectively, work should be broken down into small pieces. Which of the following does NOT describe how far to decompose the work?
A. Until it has a meaningful conclusion
B. Until it cannot be logically subdivided further
C. Until it can be done by one person
D. Until it can be realistically estimated
A
- Answer C
Explanation The lowest level of the WBS is a work package, which can be completed by more than one person. The other choices are aspects of a work package.
15
Q
15. A project manager may use to make sure the team members clearly know what work is included in each of their work packages. A. The project scope statement B. The product scope C. The WBS dictionary D. The schedule
A
- Answer C
Explanation The project scope statement describes work on a high-level basis. Work packages need to be specific to enable team members to complete their work without gold plating. The product scope does not tell team members what work is assigned to them. The team should have a copy of the schedule, but a schedule does not show them what work is included in each of their work packages. Work packages are described in the WBS dictionary. NOTE: Do not think of the WBS dictionary as a dictionary of terms.
16
Q
- The MAIN purpose of writing a user story is:
A. To document features or functions required by stakeholders.
B. To create a record of issues encountered on the project.
C. To perform what-if analysis.
D. To communicate progress.
A
- Answer A
Explanation A user story is a way of stating a requirement, often using the following format: As a , I want , so that . User stories may be developed in facilitated workshops or as part of other requirements-gathering methods.