04-Integration Management Flashcards

1
Q
The need for	is one of the major driving forces for communication in a project.
A.	Optimization
B.	Integrity
C.	Integration
D.	Differentiation
A

Answer C

Explanation The project manager is an integrator. This is a question about your role as an integrator and communicator

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The customer has accepted the completed project scope. However, the lessons learned required by the project management office have not been completed. What is the status of the project?
A. The project is incomplete because it needs to be replanned.
B. The project is incomplete until all project and product deliverables are complete and accepted.
C. The project is complete because the customer has accepted the deliverables.
D. The project is complete because it has reached its due date.

A

Answer B
Explanation Replanning is uncalled for by the situation described. Reaching the planned completion date does not mean the project is necessarily finished. A project is complete when all work, including all project management work, is complete and the product of the project and all project deliverables are accepted. The lessons learned are project management deliverables, and therefore must be completed for the project to be complete.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
When it comes to changes, the project manager's attention is BEST focused on:
A.	Making changes.
B.	Tracking and recording changes.
C.	Informing the sponsor of changes.
D.	Preventing unnecessary changes.
A

Answer D

Explanation Project managers should be proactive. The only proactive answer here is preventing unnecessary changes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The customer on a project tells the project manager they have run out of money to pay for the project. What should the project manager do FIRST?
A. Shift more of the work to later in the schedule to allow time for the customer to get the funds.
B. Close Project or Phase.
C. Stop work.
D. Release part of the project team.

A

Answer B
Explanation Every project must be closed, as closure provides benefit to the performing organization. This means simply stopping work is not the best choice. Shifting work and releasing team members do not solve the problem—they just postpone dealing with it. The best thing for the project manager to do is begin the Close Project or Phase process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
All of the following are parts of an effective change management plan EXCEPT:
A.	Procedures.
B.	Standards for reports.
C.	Meetings.
D.	Lessons learned.
A

Answer D
Explanation A change management plan includes the processes and procedures that allow smooth evaluation and tracking of changes. Lessons learned are reviews of the processes and procedures after the fact, to improve them on future projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

A work authorization system can be used to:
A. Manage who does each activity.
B. Manage when and in what sequence work is done.
C. Manage when each activity is done.
D. Manage who does each activity and when it is done

A

Answer B
Explanation Who does each activity is managed with the responsibility assignment matrix. When each activity is done is managed with the project schedule. A work authorization system is used to coordinate when and in what order the work is performed so that work and people may properly interface with other work and other people.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
7. A project is plagued by changes to the project charter. Who has the primary responsibility to decide if these changes are necessary?
A.	The project manager
B.	The project team
C.	The sponsor
D.	The stakeholders
A

Answer C
Explanation The sponsor issues the project charter and so he or she should help the project manager control changes to the charter. The primary responsibility lies with the sponsor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Effective project integration usually requires an emphasis on:
A. The personal careers of the team members.
B. Timely updates to the project management plan.
C. Effective communication at key interface points.
D. Product control.

A

Answer C
Explanation This question is asking for the most important of the choices. Think about what is involved in integration: project management plan development, project management plan execution, and integrated change control. Updates and product control are parts of project monitoring and controlling, while integration includes more than control. Advancing the careers of team members falls under project executing (the Develop Project Team process). In order to integrate the project components into a cohesive whole, communication is key whenever one activity will interface with another or one team member will interface with another, and when any other form of interfacing will occur.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
Integration is done by the:
A.	Project manager.
B.	Team.
C.	Sponsor.
D.	Stakeholders.
A

Answer A

Explanation Integration is a key responsibility of the project manager.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Which of the following BEST describes the project manager’s role as an integrator?
A. Help team members become familiar with the project.
B. Put all the pieces of a project into a cohesive whole.
C. Put all the pieces of a project into a program.
D. Get all team members together into a cohesive whole.

A

Answer B

Explanation Integration refers to combining activities, not team members.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
Approved corrective actions are an input to which of the following processes?
A.	Validate Scope
B.	Direct and Manage Project Work
C.	Develop Project Charter
D.	Develop Schedule
A

Answer B

Explanation Direct and Manage Project Work is the only correct response.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
Double declining balance is a form of:
A.	Decelerated depreciation.
B.	Straight line depreciation.
C.	Accelerated depreciation.
D.	Life cycle costing.
A

Answer C
Explanation Double declining balance is a form of depreciation. That eliminates the choice of life cycle costing. The choices of decelerated depreciation and straight line depreciation are also incorrect because double declining balance is a form of accelerated depreciation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Which of the following BEST describes what a project charter may be used for when the work is being completed?
A. To make sure all the team members are rewarded
B. To help determine if a scope change should be approved
C. To assess the effectiveness of the change control system
D. To make sure that all the documentation on the project is completed

A

Answer B
Explanation One of the ways to decide if a change should be approved is to determine whether the work falls within the project charter. If not, it should be rejected, assigned to a more appropriate project, or addressed as a project of its own

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Which of the following BEST describes a project management plan?
A. A printout from project management software
B. A bar chart
C. Risk, human resource, process improvement, and other management plans
D. The project scope

A

Answer C
Explanation The project management plan includes more than just a bar chart and the project manager’s plan for completing the work. It includes all the management plans for the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Which of the following is TRUE about the development of a project charter?
A. The sponsor creates the project charter, and the project manager approves it.
B. The project team creates the project charter, and the PMO approves it.
C. The executive manager creates the project charter, and the functional manager approves it.
D. The project manager creates the project charter, and the sponsor approves it.

A

Answer D
Explanation The project manager may create the project charter, but it is approved and authorized by the project sponsor, giving the project manager authority to proceed with the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

A project management plan should be realistic in order to be used to manage the project. Which of the following is the BEST method to achieve a realistic project management plan?
A. The sponsor creates the project management plan based on input from the project manager.
B. The functional manager creates the project management plan based on input from the project manager.
C. The project manager creates the project management plan based on input from senior management.
D. The project manager creates the project management plan based on input from the team.

A

Answer D
Explanation If we were to rephrase the question, it would be asking, “Who creates the project management plan?” The best answer is that the project management plan is created by the project manager but requires input from the team.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

You are taking over a project during project planning and discover that six individuals have signed the project charter. Which of the following should MOST concern you?
A. Who will be a member of the change control board
B. Spending more time on configuration management
C. Getting a single project sponsor
D. Determining the reporting structure

A

Answer B
Explanation Determining who will be on the change control board and determining the reporting structure may have already been done. In any case, these choices are not directly impacted by the number of sponsors who have signed the charter. Having a single project sponsor is not necessary. This situation implies that there are six areas concerned with this project. In addition to added communications requirements, you should be concerned with competing needs and requirements impacting your efforts on configuration management.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

The project manager is working to clearly describe the level of involvement expected from everyone on the project in order to prevent rework, conflict, and coordination problems. Which of the following BEST describes the project manager’s efforts?
A. Develop Project Management Plan and Plan Quality Management
B. Manage Stakeholder Engagement and Direct and Manage Project Work
C. Validate Scope and Control Quality
D. Identify Risks and Develop Project Team

A

Answer A
Explanation Notice that this question uses the words “working to clearly describe” and “prevent!’ Taken together, they should tell you the project is in project planning. This eliminates all choices except Develop Project Management Plan and Plan Quality Management. Coordination and conflict prevention relate to Develop Project Management Plan, and preventing rework is part of Plan Quality Management.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q
All of the following are parts of the Direct and Manage Project Work process EXCEPT:
A.	Identifying changes.
B.	Using a work breakdown structure.
C.	Implementing corrective actions.
D.	Setting up a project control system.
A

Answer D
Explanation A WBS is created in project planning, but can be used to help manage the project during project executing. The wording here was not “creating a WBS,” but “using a WBS.” A project control system is set up during project planning, not during project executing, and therefore is the exception

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

A project manager is appointed to head a highly technical project in an area with which this person has limited familiarity. The project manager delegates the processes of Develop Schedule, Estimate Costs, Define Activities, and Estimate Activity Resources to various project team members, and basically serves as an occasional referee and coordinator of activities. The results of this approach are likely to be:
A. A team functioning throughout the project at a very high level, demonstrating creativity and commitment.
B. A team that initially experiences some amounts of confusion, but that after a period of time becomes a cohesive and effective unit.
C. A team that is not highly productive, but that stays together because of the work environment created by the project manager.
D. A team that is characterized by poor performance, low morale, high levels of conflict, and high turnover.

A
  1. Answer D
    Explanation A project manager must manage and integrate all aspects of a project. If all activities are delegated, chaos ensues and team members will spend more time jockeying for position than completing activities.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

You are in the middle of executing a major modification to an existing product when you learn that the resources promised at the beginning of the project are not available. The BEST thing to do is to:
A. Show how the resources were originally promised to your project.
B. Replan the project without the resources.
C. Explain the impact if the promised resources are not made available.
D. Crash the project.

A

Answer C
Explanation Crashing and replanning are essentially delaying the situation. Instead, the project manager should try to prevent the situation by showing the consequences if the resources are not available. This is a more effective strategy than saying, “But you gave them to me.”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

The primary customer of a project has requested an application change during user testing. As project manager, how should you BEST address this issue?
A. Develop a risk mitigation plan.
B. Create a formal change request.
C. Inform the project sponsor of changes to scope, cost, and schedule.
D. Ensure the scope change complies with all relevant contractual provisions.

A

Answer B
Explanation Your first action is to formally document the requested change to the requirements, and then follow the integrated change control process.

23
Q

The project manager has just received a change from the customer that does not affect the project schedule and is easy to complete. What should the project manager do FIRST?
A. Make the change happen as soon as possible.
B. Contact the project sponsor for permission.
C. Go to the change control board.
D. Evaluate the impacts on other project constraints.

A

Answer D
Explanation The other impacts to the project should be evaluated first. Such impacts include scope, cost, quality, risk, resources, and customer satisfaction. Once these are evaluated, the change control board, if one exists, can approve or deny the change.

24
Q

Your company just won a major new project. It will begin in three months and is valued at US $2,000,000. You are the project manager for an existing project. What is the FIRST thing you should do once you hear of the new project?
A. Ask management how the new project will use resources.
B. Resource level your project.
C. Crash your project.
D. Ask management how the new project will affect your project.

A

Answer D
Explanation You do not have enough information to consider resource leveling or crashing this project. As you work on any project, you need to constantly reevaluate the project objectives and how the project relates to other concurrent projects. Is your project still in line with corporate objectives? If the other project will impact yours, you need to be proactive and work on options now.

25
Q
You were just assigned to take over a project from another project manager who is leaving thecompany. The previous project manager tells you that the project is on schedule, but only because he has constantly pushed the team to perform. What is the FIRST thing you should do as the new project manager?
A.	Check risk status.
B.	Check cost performance.
C.	Determine a management strategy.
D.	Tell the team your objectives.
A

Answer C
Explanation Before you can do anything else, you have to know what YOU are going to do. Developing the management strategy will provide the framework for all the rest of the choices presented and the other activities that need to be done.

26
Q
You are assigned as the project manager in the middle of the project. The project is within the baselines, but the customer is not happy with the performance of the project. What is the FIRST thing you should do?
A.	Discuss it with the project team.
B.	Recalculate baselines.
C.	Renegotiate the contract.
D.	Meet with the customer.
A

Answer D

Explanation First, you need to find out why the customer is not happy. Then meet with the team and determine options

27
Q

It is the middle of the project when the project manager is informed by her scheduler that the project control limits are secure. That same morning she receives a note from a team member about a problem he is having. The note says, “This activity is driving me crazy, and the manager of the accounting department won’t help me until the activity’s float is in jeopardy:’ In addition, the project manager has e-mails from a minor stakeholder and 14 e-mails from team members. While she is reading the e-mails, a team member walks into the project manager’s office to tell her a corrective action was implemented by a team member from the project management office, but was not documented. What should the project manager do NEXT?
A. Report the documentation violation to the project management office, evaluate the security of the control limits, and review the e-mailing rules in the communications management plan.
B. Clarify the reasoning behind documentation being a problem, get the accounting department to assist the team member, and respond to the minor stakeholder.
C. Add the implemented corrective action to the change log, discuss the value of documentation at the next team meeting, and smooth the team member’s issue with the accounting department.
D. Find out who caused the problem with the accounting department, respond to the minor stakeholder before responding to the other e-mails, and review the process listed in the communications management plan for reporting concerns with the team member having the documentation problem.

A

Answer C
Explanation Notice how many situations are thrown at you in this question. It is important to practice reading through questions to discover what is important and what is just background information. In this question, the only thing relevant was the corrective action taken. Once you discover what the primary issue is, look at the choices to find out which is best for addressing that issue. What is the primary issue here? Did you realize the team member’s note is about a non¬critical path activity? (“Until the project float is in jeopardy” means there is float and, thus, it is not on the critical path.) So is the issue the noncritical path activity or the documentation? You might disagree with the logic, but in this case the answer is the documentation. In the real world, problems often repeat. Without a record of what was done, there is no opportunity to consider the same solution for future problems. Documentation is critical to projects. Because the change log becomes part of the historical records database, it is best to first record the corrective action taken, then discuss the value of documentation at the next team meeting, and smooth the team member’s issue with the accounting department.

28
Q

The client demands changes to the product specification that will add only two weeks to the critical path. Which of the following is the BEST thing for the project manager to do?
A. Compress the schedule to recover the two weeks.
B. Cut scope to recover the two weeks.
C. Consult with the sponsor about options.
D. Advise the client of the impact of the change,

A

Answer C
Explanation Do you remember what to do when there is a change? Evaluate first. You wouldn’t take action before getting approval, so compressing the schedule or cutting scope would happen after consulting the sponsor and/or advising the client of the impact of the change. You would not go to the customer before going to your internal management, so advising the client is not the correct thing to do next. The next step is to discuss options with the sponsor.

29
Q

During project executing, the project manager determines that a change is needed to material purchased for the project. The project manager calls a meeting of the team to plan how to make the change. This is an example of:
A. Management by objectives.
B. Lack of a change management plan.
C. Good team relations.
D. Lack of a clear work breakdown structure.

A

Answer B
Explanation The project manager is asking how to make a change. Such a question cannot be resolved using management by objectives, team relations, or a work breakdown structure. The procedures, forms, sign-offs, and other similar requirements for handling changes should have already been determined in the change management plan. Because they were not, the project manager will waste valuable work time trying to figure it out after the fact.

30
Q
  1. The project was going well when all of a sudden there were changes to the project coming from multiple stakeholders. After all the changes were determined, the project manager spent time with all the stakeholders to find out why there were changes and to discover any more.
    The project work has quieted down when a team member casually mentions to the project manager that he added functionality to a product of the project. “Do not worry,” he says, “I did not impact time, cost, or quality!” What should the project manager do FIRST?
    A. Ask the team member how the need for the functionality was determined.
    B. Hold a meeting to review the team member’s completed work.
    C. Look for other added functionality.
    D. Ask the team member how he knows there is no time, cost, or quality impact.
A

Answer D
Explanation Notice that the first paragraph is extraneous. Also notice that the question states that the change has already been made. The project manager’s actions would be different if the change had not been made. The project manager, with the help of others, must determine how a change impacts the project as a whole. Asking the team member how he knows there is no impact on time, cost, or quality is the best answer. This begins the project manager’s analysis of the impacts to the project as a whole by finding out what analysis has already been done. This change minimally involves a change to the scope baseline, and likely other baselines. A change request must ultimately be submitted to integrated change control, but that is not listed as an option.

31
Q
You are asked to prepare a budget for completing a project that was started last year and then shelved for six months. All the following would be included in the project budget EXCEPT:
A.	Fixed costs.
B.	Sunk costs.
C.	Direct costs.
D.	Variable costs.
A

Answer B
Explanation Sunk costs are expended costs. The rule is that they should not be considered when deciding whether to continue with a troubled project.

32
Q
Which of the following sequences represents straight line depreciation?
A.	$100, $100, $100
B.	$100, $120, $140
C.	$100, $120, $160
D.	$160, $140, $120
A

Answer A

Explanation Straight line depreciation uses the same amount each time period

33
Q

This project is chartered to determine new ways to extend the product life of one of the company’s medium-producing products. The project manager comes from the engineering department, and the team comes from the product management and marketing departments.
The project scope statement and project planning are completed when a stakeholder notifies the team that there is a better way to complete one of the work packages. The stakeholder supplies a technical review letter from his department proving that the new way to complete the work package will actually be faster than the old way.
The project manager has had similar experiences with this department on other projects, and was expecting this to happen on this project. What is the FIRST thing the project manager should do?
A. Contact the department and complain again about their missing the deadline for submission of scope.
B. 1.00k for how this change will impact the cost to complete the work package and the quality of the product of the work package.
C. See if there is a way to change from a matrix organization to a functional organization so as to eliminate all the interference from other departments.
D. Ask the department if they have any other changes.

A

Answer B
Explanation Complaining about the missed deadline could be done, but it is not proactive. It would be helpful to get to the root cause of why this department always comes up with such ideas or changes after the project begins. However, this is not the immediate problem; the change is the immediate problem, and therefore complaining is not best. The type of project organization described is a matrix organization. There is not anything inherently wrong with such an organization, nor is there anything in this particular situation that would require it to be changed, so changing the way the company is organized cannot be best. The department’s history indicates that asking if the department has other changes is something that should definitely be done, but the proposed change needs more immediate attention. Looking at impacts of the change begins integrated change control.

34
Q
Project A has an internal rate of return (1RR) of 21 percent. Project B has an IRR of 7 percent. Project C has an IRR of 31 percent. Project D has an IRR of 19 percent. Which of these would be the BEST project?
A.	Project A
B.	Project B
C.	Project C
D.	Project D
A

Answer C
Explanation Remember, the internal rate of return is similar to the interest rate you get from the bank. The higher the rate, the better the return.

35
Q
An output of the Close Project or Phase process is the creation of:
A.	Project archives.
B.	A project charter.
C.	A project management plan.
D.	A risk management plan.
A

Answer A
Explanation The project charter is created in initiating. The project management plan and risk management plan are outputs of project planning. Project records are archived in the Close Project or Phase process.

36
Q
All of the following occur during the Close Project or Phase process EXCEPT:
A.	Creating lessons learned.
B.	Formal acceptance.
C.	Performance reporting.
D.	Performing cost-benefit analysis.
A

Answer D
Explanation Cost-benefit analysis is done earlier in the project to help select between alternatives. All the other choices are done during the Close Project or Phase process. Therefore, performing cost-benefit analysis must be the best answer

37
Q
Which of the following is included in a project charter?
A.	A risk management strategy
B.	Work package estimates
C.	Detailed resource estimates
D.	The business case for the project
A

Answer D
Explanation A risk management strategy and work package estimates are not created until project planning, but the project charter is created in initiating. A project charter may include the names of some resources (the project manager, for example), but not detailed resource estimates. Of the choices given, only the business case for the project is included in the project charter

38
Q

A project manager is trying to convince management to use more formal project management procedures and has decided to start improving the company’s project management by obtaining a project charter for each of his projects. Which of the following BEST describes why a project charter would help the project manager?
A. It describes the details of what needs to be done.
B. It lists the names of all team members.
C. It gives the project manager authority.
D. It describes the history of similar or related projects

A

Answer C
Explanation The exam will ask questions like this to make sure you know the benefits you should be getting out of the processes and tools of project management. The details of what needs to be done are found in the WBS dictionary. The names of team members are included in the responsibility assignment matrix and other documents. Project history is found in the lessons learned and other historical records. A major benefit of a project charter is that it documents the authority given to the project manager.

39
Q
Linear programming is an example of what type of project selection criteria?
A.	Constrained optimization
B.	Comparative approach
C.	Benefit measurement
D.	Impact analysis
A

Answer A

Explanation Constrained optimization uses mathematical models. Linear programming is a mathematical model.

40
Q

You have been involved in creating the project charter, but could not get it approved. Your manager and his boss have asked that the project begin immediately. Which of the following is the BEST thing to do?
A. Set up an integrated change control process.
B. Show your manager the impact of proceeding without approval.
C. Focus on completing projects that have signed project charters.
D. Start work on only the critical path activities.

A

Answer B
Explanation The best thing to do would be to show the impact. This is the only choice that prevents future problems—always the best choice. The other choices just pretend the problem does not exist.

41
Q

The engineering department has uncovered a problem with the cost accounting system and has asked the systems department to analyze what is wrong and fix the problem. You are a project manager working with the cost accounting programs on another project. Management has issued a change request to the change control board to add the new work to your project.
Your existing project has a cost performance index (CPI) of 1.2 and a schedule performance index (SPI) of 1.3, so you have some room to add work without delaying your existing project or going over budget. However, you cannot see how the new work fits within the project charter for your existing project. After some analysis, you determine that the new work and existing work do not overlap and can be done concurrently. They also require different skill sets. Which of the following is the BEST thing to do?
A. Develop a project charter.
B. Reestimate the project schedule with input from the engineering department.
C. Validate the scope of the new work with the help of the stakeholders.
D. Identify specific changes to the existing work.

A

Answer A
Explanation How long did it take you to read this question? Expect long-winded questions on the exam. Take another look at the choices before you continue reading. Did you notice that each of the choices occurs during a different part of the project management process?
This question is essentially asking if the new work should be added to the existing project. There may be many business reasons to try to do this, but from a project management perspective, major additions to the project are generally discouraged. In this case, the new work is a self-contained unit of work, has no overlap with the existing work, does not fit within the project charter, and needs a different skill set. Therefore, it is best to make it a new project.
The first step to answering this question is to realize that the work should be a separate project. The second step is to look at the choices and see which relates to initiating a new project. Reestimating the project sounds like the best choice only if you did not realize that the new work should be a separate project. Validating scope is done during project monitoring and controlling, and does not relate to the decision of whether to add work to the project. Identifying scope changes also implies that the new work has been accepted as an addition to the existing project. Developing a project charter is among the first steps of initiating a new project, and the best choice in this situation

42
Q
All technical work is completed on the project. Which of the following remains to be done?
A.	Validate Scope
B.	Plan Risk Responses
C.	Create a staffing management plan
D.	Complete lessons learned
A

Answer D
Explanation Did you pick Validate Scope? Then you may have forgotten that the Validate Scope process is done during project monitoring and controlling, not project closing. Planning the risk responses and creating the staffing management plan are done earlier in the project. The lessons learned can only be completed after the work is completed.

43
Q

Which of the following BEST reflects the phrase “influencing the factors that affect change”?
A. Telling people that changes are not allowed after planning is complete
B. Determining the sources of changes and fixing the root causes
C. Adding more activities to the work breakdown structure to accommodate risks
D. Calculating the impact of changes to date on the project

A

Answer B
Explanation A project manager should be looking at where changes are coming from and doing whatever is necessary to limit the negative effects of change on the project. He or she needs to find the root cause, so future changes may be avoided

44
Q

What is a recommended method for controlling change within a project?
A. Have only the project manager able to initiate change
B. Have each change approved or rejected through a formal change control process
C. Allow each project member ultimate control of changes within their realm of the project without a review process
D. Freeze scope and allow absolutely no changes

A

B - The change control procedure varies from project to project. However, every change request must be processed through a formal change control process. [PMBOK 5th edition, Page 96] [Project Integration Management]

45
Q
The project manager of a project calls you in as a consultant to provide inputs on developing the Project Charter. According to the PMBOK, your contribution to the project could be best termed as:
A.	Professional Consultant
B.	Expert Judgment
C.	Charter Consultant
D.	Expert Consultancy
A

B - Expert judgment is the judgment provided, based upon the expertise in an application area, knowledge area, discipline, industry etc. This is available from many sources including consultants. [PMBOK 5th edition, Page 71] [Project Integration Management]

46
Q
Which process is concerned with providing forecasts to update current cost information?
A.	Monitor and Control Project Work
B.	Project Management Information System
C.	Close Project or Phase
D.	Direct and Manage Project Work
A

A - The Monitor and Control Project Work process is responsible for keeping track of the project’s measures, including cost. [PMBOK 5th edition, Page 86] [Project Integration Management]

47
Q
Which of the following would not be considered as an Enterprise Environmental Factor during the Develop Project Charter process?
A.	Scope Statement
B.	Organizational infrastructure
C.	Governmental standards
D.	Marketplace conditions
A

A - The Scope statement is clearly not an enterprise environmental factor whereas the other three choices - Governmental standards, Organizational infrastructure, and Marketplace conditions are enterprise environmental factors. [PMBOK 5th edition, Page 29] [Project Integration Management]

48
Q
The Close Project or Phase process is not applicable for?
A.	Projects being cancelled
B.	Projects being closed
C.	Project phase being closed
D.	Projects being reactivated
A

D - The Close Project or Phase process allows the project manager to close or finish a specific phase of the project. [PMBOK Page 100] [Project Integration Management]

49
Q
Which of these tools and techniques are common to all six Project Integration Management processes?
A.	Project management Information System
B.	Analytical techniques
C.	Facilitation techniques
D.	Expert Judgment
A

D - All six processes of Project. Integration Management use Expert judgment as a tool and technique. [PMBOK 5th edition, Page 65] [Project Integration Management]

50
Q

You are beginning a new project. When should you use the Perform Integrated Change Control process?
A. Throughout the entire project
B. Only when closing out the project
C. Only after the project is completely funded
D. Only after the project scope is clearly defined

A

A - Changes can occur in the project at any time, therefore the Perform Integrated Change Control process is valuable for managing and tracking those changes. [PMBOK 5th edition, Page 96] [Project Integration Management]

51
Q
The project management team has determined that there are some changes to the Scope of the project. According to the PMBOK, who would be responsible for reviewing, evaluating and approving documented changes to the project?
A.	Change Control Board (CCB)
B.	Change Configuration Board (CCB)
C.	Scope Control Board (SCB)
D.	Configuration Control Board (CCB)
A

A - The Change Control Board is a group of formally constituted stakeholders responsible for reviewing, evaluating, approving, delaying or rejecting changes to the project. [PMBOK 5th edition, Page 96] [Project Integration Management]

52
Q

What is the difference between the Monitor and Control Project Work and the Direct and Manage Project Work processes?
A. The Monitor and Control Project Work and the Direct and Manage Project Work processes are the same.
B. The Monitor and Control Project Work process monitors the project performance while the Direct and Manage Project Work process is concerned with performing the activities to accomplish project requirements.
C. The Monitor and Control Project Work process is a sub-process of the Direct and Manage Project Work process.
D. There is no such thing as the Monitor and Control Project Work process.

A

B - The Monitor and Control Project Work process monitors the other project processes, including the Direct and Manage Project Work process, while the Direct and Manage Project Work process completes the project scope. [PMBOK Page 79, 86] [Project Integration Management]

53
Q
Which of following is not an output of the Direct and Manage Project Work process?
A.	Deliverables
B.	Work performance data
C.	Project management plan
D.	Change requests
A

C - The Direct and Manage Project Work has several outputs, including deliverables, work performance data, change requests, project management plan updates, and project document updates. The project management plan is an input to the process. [PMBOK 5th edition, Page 79] [Project Integration Management]