(08) Project Performance Flashcards
Reasons for reducing project duration.
- customer requirements
- contract commitments
- time to market matrix
- incentives, bonuses for early completion
- overhead and good will costs
- pressure to move resources to another project
Monitoring and controlling projects (definition)
Comparing actual performance against plan to identify deviations.
What deviations?
- Current status of project (schedule and cost)
- Remaining cost and date that project will be completed
- Potential problems that need to be addressed now
- Out of control activities that require intervention
- Causes of schedule and cost overruns
- Forecast of overruns at time of project completion
Crashing (formula)
slope = crash cost - normal cost / normal time - crash time
Changes (cus..)
Due to customer requests - add new features or taking out original features.
Changes (risk..)
Due to risk event - implementation of contingency plan.
Changes (pro..)
Due to suggestions from project team members - improvement.
Time Management (sch..)
Schedule control to..
- Keep track of project status.
- Determine whether there is change in schedule.
- Manage changes in schedule when they occur.
- Influence factors that cause a change in schedule.
- Tracking gantt chart, performance review, team member morale, earned value management, milestone completion dates.
Cost Management (cost control to..)
- Monitor cost performance
- Ensure only appropriate project changes are included
- Inform stakeholders of changes that will affect costs
Cost Management (cost control for..)
- Updating project management plan
- Documentation of corrective plan
- Revised estimate of project completion
- Requested changes
- Updating organisational process assets
Baseline.
The primary reference point against which we measure changes in our project
- Start and end date
- Durations
- Work and cost estimates
Tracking Gantt Chart.
Used to monitor and control projects.
- Actual performance = 1.3 million.
- Planned = 1 million. Why?
- May be ahead of schedule, $300k may represent costs for labour working ahead of schedule.
- Behind schedule.
- Therefore, need to performance EVM analysis to be sure.
EVM (definition)
A systematic project management process used to find variances in projects based on the comparison of worked performed and work planned.
Term (ear..)
Earned Value or BCWP
- Percent of original budget earned from work completed