(03) Developing the baseline network plan Flashcards
What is a Project Network Diagram?
A flow chart that graphically depicts the sequence, interdependencies and start and finish times of the project activities.
How does a Project Network Diagram work?
- Networks typically flow from left to right.
- Arrows indicate precedence and flow.
- An activity cannot begin until all of its preceding activities are complete.
- Identify each activity with a unique number.
- This number must be greater than its predecessors. - Looping is not allowed.
- Conditional statements are not allowed.
- Use common start and stop nodes.
Every activity on the network diagram must be completed for the project to finish.
What are the Benefits of a Project Network Diagram?
- Provides the basis for scheduling labour and equipment.
- Enhances communication among project participants.
- Provides an estimate of the project duration.
- Provides a basis for budgeting cash flow.
- Identifies the critical activities.
- Help managers get and stay on plan.
What is the terminology used (when Constructing a Project Diagram).
- Activity (or task).
- Path.
- Critical Path.
What is an activity (or task)?
An element of the project that requires time – e.g., A, B, C, D, etc.
What is a Path?
A sequence of connected, dependent activities.
What is a Critical Path?
The longest path through the network that allows for the completion of all project-related activities.
What is dependency?
Dependency relates to the sequencing of project activities.
What are the different types of dependencies?
- Mandatory Dependencies (Hard Logic).
- Discretionary Dependencies (Soft Logic).
- External Dependencies.
We must understand the type of dependencies required for each activity on our project.
What is a successor?
An activity that is done directly after another activity.
What are Mandatory Dependencies (Hard Logic)?
Inherent in the nature of the work itself – e.g., scrape off old paint, then apply primer, then paint the house.
What are Discretionary Dependencies (Soft Logic)?
Defined by the project team - e.g., paint room 1 first and then paint room 2.
What are External Dependencies?
Involve relationships between project and non-project activities – e.g., a shared hardware platform ordered by another department.
What is a predecessor?
An activity that is done directly before another activity.
What are the different types of dependency relationships?
- Finish-to-start relationship.
- Start-to-start relationship.
- Finish-to-finish relationship.
- Start-to-finish relationship.