(03) Developing the baseline network plan Flashcards

1
Q

What is a Project Network Diagram?

A

A flow chart that graphically depicts the sequence, interdependencies and start and finish times of the project activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How does a Project Network Diagram work?

A
  • Networks typically flow from left to right.
  • Arrows indicate precedence and flow.
  • An activity cannot begin until all of its preceding activities are complete.
  • Identify each activity with a unique number.
    - This number must be greater than its predecessors.
  • Looping is not allowed.
  • Conditional statements are not allowed.
  • Use common start and stop nodes.
      Every activity on the network diagram must be completed for the project to finish.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the Benefits of a Project Network Diagram?

A
  • Provides the basis for scheduling labour and equipment.
  • Enhances communication among project participants.
  • Provides an estimate of the project duration.
  • Provides a basis for budgeting cash flow.
  • Identifies the critical activities.
  • Help managers get and stay on plan.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the terminology used (when Constructing a Project Diagram).

A
  • Activity (or task).
  • Path.
  • Critical Path.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is an activity (or task)?

A

An element of the project that requires time – e.g., A, B, C, D, etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a Path?

A

A sequence of connected, dependent activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is a Critical Path?

A

The longest path through the network that allows for the completion of all project-related activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is dependency?

A

Dependency relates to the sequencing of project activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the different types of dependencies?

A
  • Mandatory Dependencies (Hard Logic).
  • Discretionary Dependencies (Soft Logic).
  • External Dependencies.
      We must understand the type of dependencies required for each activity on our project.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a successor?

A

An activity that is done directly after another activity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are Mandatory Dependencies (Hard Logic)?

A

Inherent in the nature of the work itself – e.g., scrape off old paint, then apply primer, then paint the house.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are Discretionary Dependencies (Soft Logic)?

A

Defined by the project team - e.g., paint room 1 first and then paint room 2.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are External Dependencies?

A

Involve relationships between project and non-project activities – e.g., a shared hardware platform ordered by another department.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is a predecessor?

A

An activity that is done directly before another activity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the different types of dependency relationships?

A
  • Finish-to-start relationship.
  • Start-to-start relationship.
  • Finish-to-finish relationship.
  • Start-to-finish relationship.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is a Finish-to-start relationship?

A

The subsequent activity cannot start until the preceding activity is finished.
- E.g. car manufacturing: painting can’t begin until the welding is finished.

17
Q

What is a Start-to-start relationship?

A

The subsequent activity can start AFTER the preceding activity has started.
- E.g. trenching 1km and then laying the pipe while continuing the trenching activity for the next kilometre.

18
Q

What is a Finish-to-finish relationship?

A

The finish of the subsequent activity depends on the finish of the preceding activity.
- E.g. testing the prototype can start while it is still developed, but has to finish after the prototype has been fully developed.

19
Q

What is a Start-to-finish relationship?

A

The finish of the subsequent activity depends on the start of the preceding activity.
- E.g. the documentation of a system cannot finish before the testing has started.

20
Q

What is the importance of Project Network Diagram?

A
  • Drawing the project network diagram places the activities in the right sequence, but…
  • We need to compute the start and finish times of the activities.
21
Q

What are the two complementary approaches (of Project Network Diagrams?)

A
  • Forward pass → earliest times

- Backward pass → latest times

22
Q

What three questions do you need to answer (for forward pass computation?)

A
  1. How soon can the activity start?
    - (early start – ES).
  2. How soon can the activity finish?
    - (early finish – EF).
  3. How soon the project can be finished?
    - (expected time – TE).
23
Q

What three things do you need to remember (for forward pass computation?)

A
  1. Add activity times along each path in the network.
    - (ES + duration = EF).
  2. Carry the EF to the next activity, where it becomes ES, unless..
  3. The successor is a merge activity. If so..
    - Select the largest EF of all its immediate predecessors.
24
Q

What four questions do you need to answer (for backward pass computation?)

A
  1. How late can the activity start?
    - (late start – LS).
  2. How late can the activity finish?
    - (late finish – LF).
  3. Which activities represent the critical path (CP)?
  4. How long can the activity be delayed?
    - (slack or float – SL).
25
What three things do you need to remember (for backward pass computation?)
1. Subtract activity times along each path starting with the project end activity. - (LF – duration = LS). 2. Carry the LS to the next predecessor to establish its LF, unless... 3. The next predecessor is a burst activity. If so.. - Select the smallest LS of all its immediate successors to establish its LF.
26
What is slack (or float)?
The amount of time an activity can be delayed after the start of a longer parallel activity or activities.
27
What is total slack?
The amount of time an activity can be delayed without delaying the entire project.
28
What is the formula for Slack?
Slack = (LS - ES) or (LF - EF).
29
What is Critical Path?
- The critical path shows the shortest time in which a project can be completed. - The series of activities that determine the earliest time by which the project can be completed. - The longest path through the network diagram and has the least amount of slack (or float). - The path containing the critical task is what is driving the completion date for the project.
30
What is the critical path analysis?
A network diagramming technique used to predict total project duration.
31
What things should you consider about Critical Path?
- If one or more of the activities on the critical path takes longer than planned, the whole project schedule will slip. - It is possible to have two or more critical paths in a project. - A critical path on a project can change as the project progresses.
32
Why is slack so important for the project manager?
- Slack allows some flexibility in scheduling, this may relieve pressure on resources that may be deployed elsewhere. - Slack can be used without affecting the overall project completion time.
33
How does the critical path help the project manager?
- The critical path enables the project manager to calculate the overall time of the project. - All activities on the critical path must be completed on time.
34
What do you need before you try to develop a schedule for your project?
- Scope definition. - Work breakdown structure with work packages. - Prerequisite logic (hard logic, soft logic, predecessor, successor). - Input from the customer about milestones and expected project completion.