05) Time Management Flashcards
What is the process of time management?
- Plan Schedule Management
- Define Activities
- Sequence Activities
- Estimate Activity Resources
- Estimate Activity Durations
- Develop Schedule
- Control Schedule
What is the key output of the Plan Schedule Management process?
Schedule management plan
What are the key outputs of the Define Activities process?
- Activity list
- Activity attributes
- Milestone list
What are the key outputs of the Sequence Activities process?
- Network diagrams
- Updates to project documents
What are some of the key outputs of the Estimate Activity Resources process?
- Activity resource requirements
- Resource breakdown structure
What are the key outputs of the Estimate Activity Durations process?
- Activity duration estimates
- Updates to project documents
What does the Develop Schedule process involve?
Creating a project schedule that is bought into, approved, realistic, and formal
What are some of the Develop Schedule process key outputs?
- Project schedule
- Schedule baseline
- Updates to the project management plan and project documents
What are the key outputs of the Control Schedule process?
- Work performance information
- Schedule forecasts
- Change requests
What are the four types of logical relationships between activities in the precedence diagramming method?
- Finish-to-start (FS): An activity must finish before the successor can start
- Start-to-start (SS): An activity must start before the successor can start
- Finish-to-finish (FF): An activity must finish before the successor can finish
- Start-to-finish (SF): An activity must start before the successor can finish
What are mandatory dependencies?
Mandatory: The order in which activities MUST be done, due to the inherrent nature of the work; also called “hard logic”
What are discretionary dependencies?
Discretionary: The order in which the organization has CHOSEN that activities be performed; also called “preferred,” “preferential,” or “soft logic”
What are external dependencies?
External: Dependencies based on the needs of a party OUTSIDE the project
What are internal dependencies?
Internal: Dependencies based on the needs of the project; may be under the control of the project team
What is a lag?
Lag: Waiting time inserted between activities