Yuqian #6 - Production Planning 3 Flashcards

1
Q

After planning at each of our levels for material, staffing, etc comes sequencing. What is sequencing?

A

We prioritise jobs assigned to a resource using some sequencing technique, policy, and/or heuristic, usually to achieve an objective such as most efficient machine/staff utilisation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Define the following terms related to sequencing: flowtime, makespan, tardiness, and critical ratio

A

Flowtime - time for job to flow through system

Makespan - time for group of jobs to be completed

Tardiness - difference between late jobs due date and its completion time

Critical ratio = (time remaining)/(work remaining) = 1 if job is on schedule, >1 if job is ahead of schedule, and <1 if job is behind schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Johnson’s Rule is a technique that can be used to determine a sequence. What are the steps involved in this technique?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Use Johnson’s Rule to to sequence the operations in the table below

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the five assumptions we make when using Johnson’s Rule?

A
  1. Job time must be known and constant
  2. Job times must be independent of sequence
  3. Jobs must follow same two-step sequence
  4. Job priorities cannot be used
  5. All units must be completed at first work centre before moving to second
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Scheduling is the last stage of planning before production begins, and can yield cost savings and productivity increases if done correctly. What are two difficulties with scheduling?

A
  1. Variability - setup times, processing times, interruptions, changess in set of jobs
  2. Uncertainty - not an exact science, so no exact method for identifying optimal schedule
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Scheduling is the last stage in the planning process before production begins. What does it involve?

A

Establishes the timing of the use of equipment, facilities and human activities in an organisation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the 9 objectives of scheduling?

A

Minimise: job lateness, response time, completion time, time in system, overtime, idle time, work-in-process inventory

Maximise: machine/labour utilisation, meeting of customer due dates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the difference between an infinite and a finite scheduling system?

A

Infinite: Loads jobs without regard to capacity, then levels the load and sequences the jobs

Finite: Sequences jobs as part of loading decision. Resources are never loaded beyond capacity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Refer to lecture notes about Hungerian method to make sure you understand it

A

MaNuFaCtUrInG

How well did you know this?
1
Not at all
2
3
4
5
Perfectly