Works Progress and Quality Management Flashcards
In relation to Acorn House, what specific construction elements were included in the progress evaluation of the weekly reports?
service disconnections, site set up, demolition, drainage, frame, external walls, cladding, floor, internal walls, roof covering, windows and doors, 1st fix m&e and joinery, plastering, screed, telecoms, 2nd fix, kitchens, sanitary ware, finishes, decorations, externals, snags.
For Acorn House, give examples of the British Standards you referred to during the project?
BS8102:2022 protection of below ground structures against water ingress.
BS8000:2014 workmanship on construction sites.
BS7671:2018 requirements for electrical installations
BS8214:2016 timber fire door assemblies
BS9999:2017 fire safety in the design, management and use of buildings
BS8000-12:1989 workmanship on construction sites. code of practise for decorative wall coverings and paintings.
For the Acorn House project, why did the Structural Engineer and Fire Consultant have to be engaged regarding the concrete panels?
Structural Engineer to advise on whether panels could be replaced.
Fire consultant to advise on compartmentation.
For Acorn House, what observations did you make against the Building Regulations?
Part M toilet distances, Part K handrail height and flexes calculations required, Part B non combustible cladding verification, Part A structure concrete panel removal.
What could you look for on site to ensure that materials are of good quality?
Quality marking
BS number
Kite marking
Note material name and research
For Acorn House, how did you assess quality on site? If quality was poor, what actions would you take?
- Reviewed the drawings, checked the BS noted on dwgs were being adhered to, checked materials had kite marks etc.
- I would advise the contractor, hold back payment for that item and only pay once the item had been rectified accordingly.
For the Fire Service decorations, what records did you keep during inspections?
- Operatives on site
- Weather conditions
- Photographs
- Notes on progress made and any issues raised
For the Fire Service decorations, why did you note the operatives on site? How would you obtain this number?
To determine whether there was enough resource in site.
I used observation in this instance but for larger sites I would observe the sign in records.
For the Fire Service decorations, why would you note weather conditions? Is this a relevant event or matter?
In case the contractor claims for inclement weather can determine if it differs from average for time of year.
Relevant event if so.
For the Cambridge Riverside project, how can you check the fire stopping was carried out correctly?
- Fire stopping labels
- Fire strategy
- Fire engineer specification
- Manufacturers guidance
For the Cambridge Riverside project, who produced the programme? Why was a tracker required?
The contractor produced an original programme and dropline programme but not on regular basis.
I therefore reviewed progress and produced a tracker to ensure I inspected each flat before, during and after.
For the Cambridge Riverside project, what did the report include to demonstrate compliance?
The report include before during and after photos, drawings showing the compartment walls and explanations
What was included in your report for the Cambridge Riverside project?
- Introduction
- Description and explanation
- Conclusion
- Photos before during and after
- Drawings with compartment walls
- Fire engineers specification and manufacturers guidance
What forms detailed progress and quality records? Why are these important?
- Track progress of stages with percentages
- Weather conditions
- Labour on site
- Quality comments
- Contractor responses and rectification comments
- Photographs
- Drawings
Why may early communication prevent delays?
- It allows all parties to know of the delays
- Potential solutions can be produced and mitigation measures can be put in place
- Client and contractor can prepare and work together
- It will not come as a surprise
Can you give examples of any mitigation measures?
- Increasing trades on site
- Resequencing works
- Shortening material lead in times
- Altering scope of works
How can you review the effect of any delays on site?
- Determine the length of delay by reviewing original programme.
- Liaising with contractor to determine how it will affect trades and materials.
- Considering mitigation measures to reduce delays.
- Review reason for delay and whether contractor is entitled to additional time and money.
What documentation specifies programme and quality requirements?
Schedule of works and form of tender
It may refer to british standards or approved docs.