Work BreakDown Structure Flashcards
1
Q
What is the Work BreakDown Structure?
A
deliverable-oriented grouping of the work involved in a project
that defines the total scope of the project.
2
Q
What are the steps in making the WBS?
A
Deliverable Oriented hierarchical decomposition of the
work to be executed by the project team
Organizes and defines total scope of the project
Sub-divides project work into smaller , more manageable
pieces
At the lowest level , work packages are generated , which
can be scheduled, cost-estimated, monitored and
controlled
3
Q
What are the inputs needed for the WBS?
A
- Organizational Process Assets
- Project Scope Statement
- Project Scope Management Plan
- Approved Change Requests