WK7PM - Time Related Flashcards

1
Q

Q1. What are the main issues in relation to time within a contract?

A
  • Obligations after completion
  • Extension of time
  • Delay / Progression
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Q2. What dates in relation to time are inserted into the CP?

A

Start date / Completion date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Q3. What is meant by the term ‘regularly and diligently’?

A

The contractor will work efficiently and to the best of their ability in order to progress works at appropriate time, cost and quality – as stated in the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Q4. Why do we have extension of time mechanisms in building contracts?

A

Helps to preserve liquidated damages and gives the contractor a % of leeway when there are delays caused by things outside of contractors control.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Q5. What are Relevant events? Give some examples

A

RE – an event causing a delay to the completion date which is caused by the client or neutral event. RE entitle C to EOT. However, does not necessarily entitle the C to claim L&E.
RM – a matter in which the client is Emp is responsible for that materially effects the progress of works enabling a claim for L&E.
Events in which extension of time can be claimed. E.g. Variations / Force Majure / Strikes / Adverse weather / Failure to provide information /Specified perils.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Q6. What is the procedure for claiming an extension of time?

A

When it becomes apparent that the relevant event will cause a delay, the contractor must give a written notice to the client identify how the delay has been caused.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Q7. What is the difference between sectional completion and partial possession?

A

Sectional completion – set completion dates for sections of work, used on large projects e.g. housing.
Partial possession – Contract may allow for the employer to take possession of part of the works before formal completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Q8. Define the term Practical Completion.

A

Practical completion is the completion of all works contained in the contract – all obligations have been met.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Q9. What are the effects of a practical completion certificate (JCT SBC16) explaining the meaning / consequence of each one?

A
  • Start of rectification period – defects liability
  • Part release of retention
  • End of insurance
  • End of L&A damages – Contractor no longer liable
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Q10. What is the difference between the Date for Completion and the Completion Date?(JCT)

A

Date for completion – The date the contractor expects for the works to be completed this may be before or after the contract completion date.
Completion date – The date work has actually been completed and actual possession is passed to the client.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Q12. What is a concurrent delay and how should they be treated?

A

2 Events at one time causing delay e.g. Snow and labour shortage.
Apportionment – Scotland – Half and half
Malmaison approach – England & Wales – Walter v Lilly case – When there are two or more events and 1 is the employer’s fault then this constitutes a relevant matter and a 3 day extension. Must be relevant.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Q14. If the MC does not complete by the completion date, what must the CA do? Why?

A

The contract administrator may issue a certificate of non-completion, this acts as a perquisite to claiming for LAD’s

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Q15. What happens if no date for completion is inserted in contract?

A

 Always ensure a date is stated
 If no date inserted in contract?
 Lose right to liquidated and ascertained damages
 Must be given possession at such time as will
enable the work to be completed by the
completion date
- C does not have to start work but may be liable for not proceeding regularly and diligently.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Q16. What are the main contractors’ obligations after completion (JCT)?

A
  • Amend/fix defects which may become apparent after completion
  • Schedule of defects released by CA 14 days after end of rectification period.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Q11. The contractor is in culpable delay by 4 weeks and whilst carrying out the final works a variation is issued as unforeseen conditions were found in the ground. This variation will delay the contractor by a further week. How much EOT can the MC claim for?

A
Culpable delay (sometimes referred to as 'contractor delay') on the other hand is a delay that is entirely the fault of the contractor. Where the contractor is culpable for a delay, they have no entitlement to an extension of time or loss and expense.
Concurrent delays – C at fault for 4 weeks, but unforeseen GC is a RE and would entitle to an EOT of a week.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Q13. If work is omitted from the project can the Date for completion be brought forward? Why?

A

The A/CA may fix a completion date earlier than previously stated if in his opinion that it is fair and reasonable having regard to any instructions for relevant omissions since the last occasion the completion dater had been fixed.