WK3PM - Contract Prep Flashcards

1
Q

Q1. What parties are named within the form of contract? (Contents page ‘Articles’ section, see page 4 &5)

A

Contractor / Architect / Contract Admin / QS / Principal Designer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Q2. Using the contents page within the form of contract, state which section relates to the following contract administration issues:

A

a. Contractors obligations relating the materials, goods and works to be carried out, during the project: 2.3 (2)
b. Sub-contracting: 3.7-3.9 (3)
c. Payment (Interim Payments): 4.8 (4)
d. Changes to the works or design: (5)
e. Insurances: (6)
f. Procedures used to resolve disputes: (9)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Q3. Explain the purpose of the ‘Articles’ and ‘Contract Particulars’

A

Articles – Primary clauses / Sets out agreement – identifies rights, acts and forbearances
Contract Particulars – How its adapted to suit the client and project e.g. Completion dates etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Q4. List the duties of the Contract Administrator named within the Articles? (pg 4)

A
  • Issue architects’ instructions
  • Issuing payment certificates
  • Extensions of time
  • Check quality
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Q5. What is the purpose of a Bills of Quantities document under this form of contract? (pg 2) How does this differ from NEC 4?

A

• Provide rates for works
• These rates used for variations
• Specifies quality and quantity used for valuations
NEC4 – Bill of Quantity is used for tender purposes and once on site use rates for valuing but its remeasured.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Q6. Describe the purpose of the ‘Contractors Design Portion’, (Ninth recital pg 3) and the use of the Employers Requirements and Contractors Proposals relating to this section (Eleventh recital pg 3)

A

Allows for the contractor to design a portion. The client produces Employer requirements such as performance specification (minimum requirements or standard) and the contractor produces a design proposal (issues contractors’ proposal).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Q7. List 5 number items within the Contract Particulars which need to be complete as either ‘apply / not apply’

A

Supplemental provisions

  • Collaborative working
  • H&S
  • Cost savings and value improvements
  • Sustainable development and environmental considerations
  • Performance indicators
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Q8. List 5 items within the Contract Particulars where a default clause will be used if the item has not been completed.

A
  • Rectifcation period - default 6 months
  • Fluctuation provision - option A applies
  • interim payments - valuation dates - default one month after possession
  • Retention rate - 3%
  • Works insurance - professional fees - default 15%
How well did you know this?
1
Not at all
2
3
4
5
Perfectly