WK5PM - Valuations Flashcards

1
Q

Q1. Why do construction projects have interim valuations carried out?

A

Housing grants & Construction acts – Have to pay instalments to aid subcontractors cash flow on projects longer than 45 days. Either paid monthly or on agreed dates.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Q3. What items are included in an interim valuation giving a brief description of each.

A

Measured works – physical progress on site / Preliminaries / Variations / Day work / measurements on and off site / Retention / provisional sums or prime cost sums / fluctuations / loss and expense

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Q4. What is the difference between the fluctuation clauses under JCT SBC 16? Why might you recommend a Client to use the different fluctuation clauses?

A

JCT 2011 – stated all fluctuations / JCT 2016 – add as an amendment

Fluctuation A – Government tax’s and levies – only applicable if bought in before the base date.

Fluctuation B – Labour and Material costs and tax – Option A – based on basic list which client will include which are on fluctuation prices.

Fluctuation C – Formula adjustment – base rate and new

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Q5. What are the ways in which a contract sum can be adjusted giving examples under JCT SBC16?

A
  • Variations / postponements
  • Fluctuations
  • Loss and Expense
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Q6. What are the requirements for paying Materials On Site and Off site under JCT SBC 16? 7. What is the difference between a defined provisional sum and an undefined provisional sum?

A

Materials on site – Must be able to see that they are there, secure, protected, that the contractor has paid for them and must be incorporated in to the works within a month
Materials off site – Has a resting certificate, insurance against specified perils, must be clearly identified with name on.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

-

A

-

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Q8. What is retention? Why is it used? How is retention treated under JCT 16?

A

Retention is a percentage held back by the client to ensure works are completed to the right standard.
Automatically 3% if not amended.
e.g. ½ Final cost, ½ warranty release, ½ on Project Completion, ½ on final certificate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Q9. What is a payless notice - what are the rules for using one?

A

A certificate of what will be paid – Valuation minus liquidated damages etc.

  • The C must issue a PLN within 5 days of the payment.
  • Must set out basis for calculation
  • Notified sum payable by final date of payment.
  • If C fails to issue PLN, C may issue a default payment notice. The final date is extended by the period between when client should have issued and when C issued payment notice.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Q10. What is a final account?

A

The final payment - Contract sum +/- Architects instructions +/- Loss & Expense +/- Fluctuations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Q11. What is the effect of a final certificate (JCT)?

A

Instigates the release of the retention – all monies will be paid
States the value of the project and what contractor will be paid & stated the contractor has meet all obligations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Q12. Can you explain how you value preliminaries for an Interim Valuation (IV) under JCT SBC 2016?

A

Using prelim rates given with the tender.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Q13. If a project is delayed how do you amend the preliminaries value in the next IV?

A
  • Either based on weekly rates – BOQ

* Or as an agreed sum

How well did you know this?
1
Not at all
2
3
4
5
Perfectly