Which process are we talking about? Flashcards
Management or Sponsor is working with the Project Manager to fix the scope and explain the benefits of the project as well as trying to authorizing the project.
Develop Project Charter
The Project Manager is trying to push back with the management / sponsor to formally grant him authority for the execution of the project.
Develop Project Charter
Discussion about how soon the project manager should be appointed in a project.
Develop Project Charter
Project Manager is ascertaining / documenting the overall assumptions in the project.
Develop Project Charter
Establishing / documenting the baselines
Develop Project Mngt Plan
Establishing / documenting cost baseline
Determine budget
Establishing / documenting scope baseline
Create WBS
Establishing / documenting schedule baseline
Develop Schedule
Hold a kick-off meeting
Develop Project Mngt Plan
Generating deliverables of the project.
Direct and Manage Project Work
Work Performance Data has been collected or being collected.
Direct and Manage Project Work
Managing knowledge and information
Manage Project Knowledge
The Lessons Learned Register is being documented / created.
Manage Project Knowledge
Communities and Interest Groups are being generated, Knowledge Cafes and Fairs are being organized, Story Telling sessions are being held or Work Shadowing / Reverse Shadowing is being done.
Manage Project Knowledge
Work performance report
Monitor and Control Project Work
Earned Value Analysis
Control Costs
Deciding whether to approve or reject a Change Request.
Perform Integrated Change Control
Inviting Change Control Board (CCB) to take a decision on a Change Request
Perform Integrated Change Control
Conducting Configuration Management or Identification and Selection of Configuration Items or Record and Report Configuration Item Status or Perform Configuration Item Verification and Audit.
Perform Integrated Change Control
Creating / documenting / entering decisions in Change Log
Perform Integrated Change Control
Organizing an urgent / emergency change request approval decision
Perform Integrated Change Control
Regression Analysis
Close Project or Phase
Administrative closure
Close Project or Phase
Submitting the Final Report
Close Project or Phase
Handing Over, Project documents archival, ramping off the project team, understanding if the objectives of the project were met.
Close Project or Phase
Documenting stakeholder needs.
Collect Requirements
Documenting how the project and product scope would be defined, documented, validated and controlled.
Plan Scope Management
Making a detailed description of the project and product.
Define Scope
Subdividing project deliverables and work into smaller and more manageable components
Create WBS
Monitoring the status of the project and product scope.
Control Scope
Formalizing acceptance of project deliverables
Validate Scope
Managing changes to the scope / scope baseline.
Control Scope
User Stories being documented and analyzed
Collect Requirements
Business Analyst interacting with the stakeholders of the project
Collect Requirements
Prototype is being made / built
Collect Requirements
Product analysis is being conducted
Define Scope
Scope baseline is being created or finalized
Create WBS
Customer is in the process of inspecting the deliverables.
Validate Scope
The project manager is actively engaged in preventing any scope creep and preventing instances of gold plating.
Control Scope
The questions mention “Rolling Wave Planning”.
Define Activities
The project team / stakeholders are working on deciding on the unit of measure for durations, level of accuracy and setting variance thresholds.
Plan Schedule Management
The project team / stakeholders are conducting meetings with SME’s to make a list of Activities and Milestones.
Define Activities
Question mentions “Decomposition of Activities”.
Define Activities
Question mentions the making of PDM or a Network Diagram or AON or Project Schedule Network Diagram.
Sequence Activities
Project Manager / Team / Stakeholders are conducting Dependency Determination and Integration.
Sequence Activities
Project Manager is conducting Beta Distribution for duration estimating.
Estimate Activity Duration
The Project Manager is documenting and noting the assumptions and constraints that have been considered for durations for activities.
Estimate Activity Duration