Group ITTOs Flashcards

1
Q

Name group inputs (3)

A
  1. Business documents
  2. Project mngt plan
  3. Project documents
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Name business documents

A
  1. Business Case

2. Benefits Mngt Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Name project mngt plan documents/inputs

A
  1. Scope Mngt Plan
  2. Requirements Mngt Plan
  3. Schedule Mngt Plan
  4. Cost Mngt Plan
  5. Quality Mngt Plan
  6. Resource Mngt Plan
  7. Communications Mngt Plan
  8. Risk Mntg Plan
  9. Procurement Mngt Plan
  10. Stakeholder Engagement Plan
  11. Scope Baseline
  12. Schedule Baseline
  13. Cost Baseline
  14. Configuration Mngt Plan
  15. Change Mngt Plan
  16. Development Approach
  17. Performance Measurement Baseline
  18. Project Lifecycle Description
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Which document fall under the category of Project Documents? (34) - A - M

A
Activity Attributes  
Activity List  
Assumption log
Basis of Estimates  
Change Log  
Cost Estimates  
Cost Forecasts  
Duration Estimates  
Issue Log
Lessons Learned Register                    
Milestone List
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Which document fall under the category of Project Documents? (34) - P - Q

A

Physical Resource Assignments
Project Calendars
Project Communications
Project Schedule
Project Schedule Network Diagrams
Project Scope Statement
Project Team Assignments
Quality Control Measurements
Quality Metrics
Quality Reports

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Which document fall under the category of Project Documents? (34) - R - Z

A

Requirements Documentation
Requirements Traceability Matrix
Resource Calendars
Resource Breakdown Structure
Resource Requirements
Risk Register
Risk Report
Schedule Data
Schedule Forecasts
Source Selection Criteria
Stakeholder Register
Team Charter
Test and Evaluation Documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Name categories of tools and techniques by their function

A
Data gathering
Data analysis
Data representation
Decision Making
Communication
Interpersonal and team skills
Estimating
PMIS
Expert judgment
Meetings
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the purpose of Data gathering TT?

A

To Collect or generate information and data in an unbiased manner from the various stakeholders.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Which are Data gathering techniques.

A
1 Brainstorming  
2 Focus Groups  
3 Interviews  
4 Questionnaires And Surveys  
5 Checklists  
6 Check Sheets  
7 Statistical Sampling  
8 Market Research  
9 Benchmarking
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the purpose of Data Analysis TT?

A
  • Analyzing gathered data
  • Generating information and trends on different aspects of the project
  • Analysis and use of data for informed decision making.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Which are Data Analysis TT? (27)

A
1 Alternatives Analysis          
2 Assumption And Constraint Analysis          
3 Cost Of Quality
4 Cost-Benefit Analysis  
5 Decision Tree Analysis         
6 Document Analysis  
7 Earned Value Analysis  
8 Influence Diagram          
9 Iteration Burndown Chart          
10 Make-or-Buy Analysis          
11 Performance Reviews                   
12 Process Analysis          
13 Proposal Evaluation          
14 Regression Analysis  
15 Reserve Analysis          
16 Risk Data Quality Assessment          
17 Risk Probability And Impact Assessment          
18 Assessment Of Other Risk Parameters          
19 Root Cause Analysis  
20 Sensitivity Analysis          
21 Simulations          
22 Stakeholder Analysis        
23 SWOT Analysis          
24 Technical Performance Analysis          
25 Trend Analysis  
26 Variance Analysis  
27 What-if-scenario Analysis
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Purpose of Data Representation TT?

A
  • To present data and information to stakeholders.
  • To elicit getting more information from stakeholders by presenting data in a way that motivates stakeholders.
  • For decision making
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Which are Data Representation TT. (15)

A

1 Affinity Diagrams
2 Cause-And-Effect Diagram
3 Control Charts
4 Flowcharts
5 Hierarchical Charts
6 Histogram
7 Logical Data Model
8 Matrix Diagrams
9 Mind Mapping
10 Probability And Impact Matrix
11 Responsibility Assignment Matrix
12 Scatter Diagrams
13 Stakeholder Engagement Assessment Matrix
14 Stakeholder Mapping/Representation
15 Text-Oriented Formats

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Which are Decision Making TT? (4)

A

Autocratic Decision Making
Multicriteria Decision Analysis
Prioritization/Ranking
Voting

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the purpose of Interpersonal and Team Skills?

A

To be able to work with stakeholders and team members in a way to get best out of them / handle conflicts / motivating them

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Which are Interpersonal and Team Skills (17)?

A
1 Active Listening
2 Communication Styles Assessment
3 Conflict Management
4 Cultural Awareness
5 Decision Making
6 Emotional Intelligence
7 Facilitation
8 Influencing
9 Leadership                    
10 Meeting Management                    
11 Motivation
12 Negotiation  
13 Networking
14 Nominal Group Technique 
15 Observation/Conversation 
16 Political Awareness
17 Team Building
17
Q

What is the meaning of being a good communicator / having good communication skills?

A

Effective and efficient communications

18
Q

Name communication skills (4).

A

Communication Competence
Feedback
Nonverbal
Presentations

19
Q

Name Group Outputs

A

Project Mngt Plan Updates

Project Documents Updates