Week 8 - Little’s Law And Theory Of Constraints Flashcards

1
Q

What is the difference between lead time and cycle time?

A

Lead time is measured by elapsed time (minutes, hours etc) but cycle time is measured by the amount of time per unit (e.g minutes per hours/customer/unit etc)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Formula for throughput efficiency

A

Work content (time to build a unit) / lead time x 100

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What was Shingo’s P-D ratio?

A

The time to Produce a product / the time given by the customer to Deliver the product

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the formula for throughput rate?

A

1/cycle time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Formulas for lead time (2)

A

• Cycle time x WIP
• Wip/throughput rate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Formula for Little’s law in operations (2)

A

• L = λW
• L is the average number of customers in a stable system, λ is equal to the throughput rate, W is the time a customer spends in the system

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is meant in theory of constraints?

A

The speed at which an operation can run is determined by one step which is the bottleneck - bottlenecks limit the speed of an entire operation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Why is a bottleneck an important focus area?

A

Because if a bottleneck’s capacity can be increased it will increase the system capacity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Example of a bottleneck

A

The dryer is the bottleneck as it is slower than the process in front of it

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Define lead time

A

Is the average length of time it will take a new set of inputs to move all the way through the operation, assuming no unusual measures are taken

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Formula for direct labour utilisation

A

WIP / Number of operators

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Little’s law applied to a balanced line:
What is throughput rate?
What is the cycle time?
What is the WIP?

A

• Throughput rate is 20 units per hour
• Lead time is 15 minutes
• Wip is = number of operators

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How do you calculate the balancing loss? (3)

A

• Sum the difference between the balance cycle time and the unbalanced cycle time
• The divide that by number of operators multiplied by the balance cycle time for one operator
• Then get a percentage which shows the amount of employee and working time lost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly