Week 7 Flashcards
What is a Linear Activity?
A general definition of a linear activity is an activity that progresses along a physical path.
- Continuous Full-span Linear - CFL,
- Intermittent Full-span Linear - IFL,
- Continuous Partial-span Linear - CPL, and
- Intermittent Partial-span Linear - IPL
What is a Continuous Activity?
a linear activity that is expected to be in
continuous operation from the time it
begins until the time it completes.
What is a Intermittent Activity?
a linear activity that is not expected to be in continuous operation, but rather starts and stops to pace a preceding continuous activity.
An example of an intermittent activity would be a grade preparation activity that follows a concrete removal activity on a highway reconstruction project.
What is a Full-span Activity?
an activity that covers the entire course or span of the project or planning area.
What is a Partial-span Activity?
an activity that covers only a portion of the project or planning area.
What is a Bar Activity?
A bar activity, represented by a vertical bar on the linear schedule represents an activity or group of activities that occur at a particular location.
The area occupied by the bar activity is small with respect to the area of the project.
Typical activities represented by bars on a linear schedule include bridges, culverts, and storm sewer intakes.
What is the Least distance/time interval (LTI)?
The least time interval (LTI) identifies points where the buffer between activities is at a minimum
What is the Least Distance Interval (LD)?
The shortest distance between any two adjacent activities that lies within the coincident duration and intersects the least time interval.
What is the Least Time Interval? (LT)
The shortest time interval between any two adjacent (consecutive) activities.
The interval will always occur at a vertices of at least one of the activities.
How do you identify the controlling activity path (CAP)?
The determination of the critical path is the fundamental concept that makes all of the analysis provided by CPM possible.
The development of the CAP in the linear scheduling model makes CPM-type analysis of linear schedules possible.
Controlling activities: have no float.
Non-controlling activities: have float.
In linear schedule, the predominant factor determining duration is productivity (production rate).
The concept of float needs to be redefined.
Define Controlling activity path
The controlling activity path is defined as the continuous path of longest duration through the project and defines the sequence of activities that must be completed as planned to finish the project within the overall planned
duration.
What is the goal of the Upward pass?
The goal of the upward pass is to determine which activities or portions of activities could potentially be controlling.
What is the purpose of the Downward pass?
The purpose of the downward pass is to determine which portions of the potential controlling segments are actually on the controlling activity path.
What is a Delay?
A Delay is the action or condition that results in finishing a project later than stipulated in the contract.
What are the causes of delays?
- weather
- covid
- machinery issues
- lack of issues
- labour shortage
- ground conditions
Some important notes:
• Most modern construction contracts include a fixed completion date.
• In commercial contracts at least, this will frequently be coupled with liquidated damages for late completion