Week 5 Flashcards
1
Q
What is Work Breakdown Structure (WBS)?
A
Work Breakdown Structure (WBS) is a decomposition of the work into smaller or more detailed components. The WBS has multiple levels. The lowest level of the WBS is the detail cost account.
• The WBS decomposes the project into smaller components and more manageable units of work called work packages.
2
Q
What is Work Package?
A
- Work package is a task at the lowest level of the WBS.
- Work package makes it possible to develop a project plan, schedule, and budget, and then later to monitor the project’s progress.