Week 39 Chapter 21 Part 2 - Pages 21-36 to 21-69 Flashcards
The United States National Computer-Aided Design (CAD) Standard is developed and administered by the:
a. National Institute of Standards and Technology (NIST)
b. Construction Specifications Institute (CSI)
c. American Institute of Architects (AIA)
d. National Institute of Building Services (NIBS)
d. National Institute of Building Services (NIBS)
p 21-48
The NIBS wrote the introduction and is responsible for the administration and development of the standard
In the MasterFormat 2012 numbering system, Division _____ is titled “Electrical.”
a. 27
b. 26
c. 17
d. 16
b. 26
p 21-45 Table 21.1
Telecom or Communications is Division 27
A ___ type of specification allows contractors to choose the materials and installation methods to provide the desired results.
a. Reference
b. Design-build
c. Descriptive
d. Performance
d. Performance
p 21-43
Specifications are one of the elements produced during the design phase of a construction project. Performance— The focus is on results. Contractors can choose the materials and installation methods to provide the desired results.
In a _____ bid, bids and contracts for the mechanical, plumbing, and electrical portions of the project must be separate from the general construction contract.
a. Negotiated
b. Segregated
c. Syndicated
d. Multiple prime
d. Multiple prime
p 21-38
in the United States, bidding laws often require the mechanical, plumbing, and electrical portions of the work to be bid and contracted separately from the general construction contract. This is called a multiple prime bid or filed sub bid.
Once bids are received from the contractors, this type of delivery method ___, is where the owner and design professional will review these bids to award the contract.
a. Design-bid-build (DBB)
b. Design-build (DB)
c. Construction manager (CM) at risk
d. Integrated project delivery (IPD)
a. Design-bid-build (DBB)
p 21-37
The final phase is the construction phase, which consists of construction of the facility. The design professional typically will also have a role in overseeing the contraction at the owner’s request.
In this delivery process ___, the construction typically is overlapping the design phase. This allows for an expedited schedule while minimizing any potential risk for the owner.
a. Design-bid-build (DBB)
b. Design-build (DB)
c. Construction manager (CM) at risk
d. Integrated project delivery (IPD)
b. Design-build (DB)
p 21-37
Unlike the DBB scenario, the design professionals generally work directly for the contractor.
This approach ___ integrates all aspects of the design and construction process into a single team effort. This includes design professionals, CMs, and contractors.
a. Design-bid-build (DBB)
b. Design-build (DB)
c. Construction manager (CM) at risk
d. Integrated project delivery (IPD)
d. Integrated project delivery (IPD)
p 21-37
IPD uses a three-pronged platform with the owner as one entity, the design professionals as the second, and the contractors as the third.
With this form of contract, ___ , there can be a shared savings clause or incentives for early completion.
a. Stipulated sum
b. Cost plus fee
c. Unit price
b. Cost plus fee
p 21-41
This form of contract often leads to value engineering that can generate savings during the construction phase of the building.
In the design-build (DB) project delivery method, the design professionals generally work directly for the:
a. Architect
b. Consultant
c. Contractor
d. Owner
c. Contractor
p 21-37
Unlike the DBB scenario, the design professionals generally work directly for the contractor.
Before the 2004 edition, the MasterFormat included _____ divisions, with the telecommunications scope of work (SoW) included in Division _____.
a. 20; 19
b. 20; 16
c. 19; 19
d. 16; 16
d. 16; 16
p 21-44
Before the 2004 edition, the MasterFormat included 16 divisions as well as a summary of the front-end requirements. Telecommunications SoW was included within the electrical scope of Division 16.
A ___ type of specification allows contractors to choose the materials and installation methods to provide the desired results.
a. Reference
b. Design-build
c. Descriptive
d. Performance
d. Performance
p 21-43
Performance—The focus is on results. Contractors can choose the materials and installation methods to provide the desired results.
A ___ type of specification requirements are based on an established standard.
a. Reference
b. Design-build
c. Descriptive
d. Performance
a. Reference
p 21-43
The Uniform Drawing System (UDS) specified in the United States National Computer-Aided Design (CAD) Standard is produced by the:
a. National Institute of Standards and Technology (NIST)
b. Construction Specifications Institute (CSI)
c. American Institute of Architects (AIA)
d. National Institute of Building Services (NIBS)
b. Construction Specifications Institute (CSI)
p 21-48
NIBS wrote with introduction and is responsible for the administration and development of the CAD standard. AIA produces the CAD Layer Guidelines. CSI produced the Uniform Drawing System (UDS).
In the MasterFormat 2012 numbering system, the Communications division is located in the ___ Subgroup.
a. Site Services
b. Infrastructure Services
c. Site and Infrastructure
d. Facility Services
d. Facility Services
p 21-45 Table 21.1
Which one of the following types of symbols in the United States National CAD Standard (NCS) is scale dependent?
a. Reference
b. Line
c. Identity
d. Template
d. Template
p 21-54
Template—Resemble the actual objects being symbolized. These symbols are scale dependent.