week 3 Flashcards

1
Q

what is the purpose of the project planning phase

A

establishing….
- buisness requirements
- costs
- schedules
- resources plan
- delivery dates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Basic processes of project planning

A
  • scope planning
  • preparing work breakdown structure
  • project schedule development
  • resource planning
  • budget planning
  • procurement planning
  • risk management
  • quality planning
  • communication planning
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

what does a scope statement include

A
  • project name
  • project charter
  • owner, sponsor etc.
  • problem statement
  • project goals
  • requirements
  • deliverables
  • exclusions
  • milestones
  • cost estimates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

the project schedule

A

includes: sequence of activities, duration planned for each activity

created: AFTER scope planning, BEFORE resource planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

types of predecessors

A

external: outside the project

discretionary: matter of preference

mandatory: can’t do following task until predecessor is done (eg. invitations must be done before mailed)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

LEADS vs LAGS

A

LAG: one task must wait in relation to another task

LEAD: Task must start before the predecessor is done

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Types of slacks

A

total slack: allowable delay without delaying project completion

free slack: allowable delay without affecting start of following activity

safety slack: allowable delay of activity if all predecessors finish as late as possible

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

steps to apply critical path

A
  1. list activities
  2. identify dependencies
  3. create network diagram
  4. task duration estimation
  5. critical path calculation
  6. float calculation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

pros and cons of critical path

A

PRO: improve future planning, improve resource management

CON: estimating end date of activity can be difficult, networks can be complex

How well did you know this?
1
Not at all
2
3
4
5
Perfectly