W11 Project Management Flashcards

1
Q

Programme

A

A collection of projects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Project management

A
  • Organize complex, coupled processes
  • Establish schedule and plan
  • Manage budget and control costs
  • Promote teamwork and collaboration
  • Manage integration and operate at a higher level with business, marketing, sales,
    customers
  • Retain knowledge/Learn from failure
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Gannt Charts Advantages

A
  • Simple to draw/read * Useful for static projects * Provide overview * Widely recognized * Ubiquitous software
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Gannt Charts Disadvantages

A
  • Difficult to update
    manually
  • False sense of certainty * No optimization
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Project

A

A Project is a temporary endeavour undertaken to create a unique product, service or result

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Project timing

A
  • The activities required to achieve project goal: The list of every action that should be completed
    for the project to succeed.
  • The time that is required to finish each activity
  • Resources that are required to finish each activity: These include people, tools, machines,
    infrastructure, etc.
  • The interdependencies of activities on each other (Logic): Highlighting the temporal order
    of the activities in relationship to other activities (i.e. when an activity can only start when
    certain other activities have been completed)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Gannt chart

A

The Gantt chart is a bar chart that shows the activity breakdown of the project on one axis and the
timings of the tasks on the other axis. Time dependencies and resources for each task can also be
displayed on these charts. They are simple to use and understand and can be used for presenting the
time elements of projects in a simple manner.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Network Diagrams

A

In order to perform CPA and PERT and to show the interdependency logic of a project, network
diagrams are used. There are two types of these diagrams: Activity-on-Arrow and Activity-on-Node

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Activity on Arrow

A

By definition an event has a zero time duration and represents
a single state in the project (i.e. denotes the start or end of an activity
or a set of activities).The activity has a time and a name associated with it
An activity starts from an event and ends in an event

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Logic in AoA principles and constraints

A
  1. An event does not happen until all activities leading to it are complete.
  2. No activity can start until its start event is complete.
    * A network is a collection of interrelated events and activities
    * A network should start and end with an event (called start and end)
    * Time moves from left to right (Just to make things simple)
    * The start event is the only event in the network without activities leading into it and the end
    event is the only event in the network without activities leading out.
    * Loops are disallowed and no two activities can have both the same start and the same end
    events.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The Dummy Activity

A

When it becomes necessary to draw two activities with same start and finish events a dummy activity
with a zero duration can be added to preserve the logic of the diagram without breaking constraint

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Critical Path Analysis

A
  1. Make a forward calculation pass: Determine the earliest time for each event. Commence at the
    start event and traverse the activities in the network to find the earliest time that is possible
    for an event to take place. This pass finishes when the earliest possible time for the end event
    is determined. This number is equal to the minimum duration of the project.
  2. Make a backward calculation pass: Commence at the end event and traverse the network
    backwards, this time calculating the latest possible time that each event can take place given
    the end time of the project. This pass finishes when the latest possible time is determined in
    the start event.
  3. Identify the critical path in the project: This is the path formed by events for which the earliest
    and latest times are identical.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Total Float

A

When an activity is non-critical (i.e. it is not part of the critical path), its duration can expand
without affecting the rest of the project. The total float (TF) is the time by which an activity can
expand until it becomes critical and further expansion would cause the project to be delayed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Free float

A

Free float (FF) is the amount of time by which an activity can expand without affecting the start
time of any of the following activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly