Variations Flashcards
1
Q
What is the period for a contractor to respond to a schedule 2 quotation?
A
21 days
2
Q
What are disadvantages of a schedule 2 quotation
A
need to pay for the cost of putting it together even if the change isn’t instructed
3
Q
Can an instruction go ahead without an agreed price?
A
Yes unless under a SBC a schedule 2 quotation has been requested