When must the CA provide an assessment for the L&E claim?

A

Within 28 days of receipt of initial Contractor assessment.
And then 14 days after any update

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the types of relevant matter?

A
  • Variations
  • Postponement of work
  • Instruction of a prov sum
  • opening up non-defective works
  • discrepancy/divergence of contract info
  • Reasonable objection to Names Sub-Contractors/their insolvency
  • Antiquities
  • impediment, prevention, or default of the client/their team
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How can a contractor prove loss and expense?

A
  • Time sheets
  • Invoices
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What can be included in a Loss and Expense claim

A

Any actual loss:
- Management and Staff
- Equipment and plant
- Site welfare/consumables
- Interest for late release of retention
- OH&P
- Thickened prelims

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the NEC version of Relevant Matter?

A

Compensation event (deals with time and money)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

For concurrent delay, what is the effect on loss and expense?

A

if both events would have caused the delay, then time is given but not money (De Beers v Atos 2010)