Completion Flashcards
1
Q
Whats the Final Account timeline under SBC?
A
6 months after PC the Contractor will provide all info necessary to ascertain a FA
1 month remainder is given if they fail to do so
3 months for the CA to respond
2
Q
Whats the Final Account timeline under DB?
A
3 months after PC, the contractor will provide info to ascertain FA
3
Q
Whens the latest you can raise an instruction for defects period?
A
14 days after the expiry of the rectification period