Unit 14 Flashcards

1
Q

Project

A
A project is defined/characterized by:
Multiple activities
Dependencies among activities
Interdisciplinary activities
Team-based execution
Risk
Budgets
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Principles of Project Management:

The Need for Project Management

A

Categories of project success
Successful projects –on time, within budget, on scope
Challenged projects –failure in one area
Failed projects –cancelled or not used
Recent years have seen some improvement, but still 1/3 to 1/2 of projects are challenged or fail

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The Need for Project Management

A

Reasons for failure
Undefined project management practices
Poor IT management and poor IT procedures
Inadequate executive support for the project
Inexperienced project managers
Unclear business needs and project objectives
Inadequate user involvement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Project Manager Responsibilities

A

Internal Responsibilities Developing the project scheduleRecruiting and training team membersAssigning work to teams and team membersAssessing project risksMonitoring and controlling project deliverables and milestones

External ResponsibilitiesReporting the project’s status and progressWorking directly with the client (the project’s sponsor) and other stakeholdersIdentifying resource needs and obtaining resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Additional Project Stakeholders

A

Client
the person or group that funds the project

Oversight Committee
clients and key managers who review the progress and direct the project

Users
the person or group of people who will use the new system

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

PMBOK

A

Project Management Body of Knowledge

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the 10 Project Mnagaement Body of Knowledge Areas

A
Project Integration Management
Project Scope Man.
Project Time Man
Project Cost Man.
Project Quality
Project Human Resource Man.
Project Communications Man. 
Project Risk Man.
Project Procurement Man.
Project Stakeholder Man.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Schedule the Work

A

Gantt Chart
Shows task, duration, start date, predecessors, and resourcesGenerates chart graphically showing dates, predecessors, tasks, and critical path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

PERT/CPM chart

Critical Path

A

Earliest start time – the earliest time that a task can begin due to predecessor durations
 Latest start time – the latest time that a task can start to maintain the schedule
 Slack time – the amount of time a task or leg of sequential tasks can be delayed without impacting the project schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Uncertainty in Duration Estimations

A

The duration is expressed using
OptimisticPessimisticMost likely times
Some assumptions about distributions
PERT analysis gives details such as the probability of completing the project in a given number of periods

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Staff and Allocate Resources

A

Staffing activity tasks consists of 5 tasks:
Developing a resource plan for the project
Identifying and requesting specific technical staff
Identifying and requesting specific user staff
Organizing the project team into work groups
Conducting preliminary training and team-building exercises

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Evaluate Work Processes:Retrospective

A

Are our communication procedures adequate? How can they be improved?Are our working relationships with the user effective?Did we hit our deadlines? Why or why not?Did we miss any major issues? How can we avoid this in the future?What things went especially well? How can we ensure it continues?What were the bottlenecks or problem areas? How can we eliminate them?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Monitor Project Progress and Make Corrections

A

Process to monitor and control project execution

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Monitor Project Progress and Make Corrections 2

A

Sample Issues-Tracking Log

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Project Schedule

A

Tracking Gantt Chart

How well did you know this?
1
Not at all
2
3
4
5
Perfectly