UK Flood Management Scheme Case Study — Jubilee River Flashcards

Why the scheme was required; the management strategy; the social, economic, environmental issues

1
Q

Location

A

Relief channel runs through Windsor, Maidenhead, Eton (West of Greater London);
Parallel to River Thames

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Quick Facts

A

Constructed in late ‘90s and early ‘00s;
11km long, 50m wide;
Protects over 3000 properties

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Social (para.1)

A

People living in path need to relocate;

Settlements downstream suffer from increased flooding (moral question)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Economic (para.2)

A

Expensive —> £110 million;
Ran out of funds + needs serious maintenance;
Takes a long time to build and be effective

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Environmental (para.3)

A

Habitats are flooded and disturbed through construction;
Water level changes —> unreliable habitat;
Unattractive in low flow due to exposed concrete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly