U6 Contract Practice - Standard Forms Flashcards
List some of the principal sources of Standard forms of contract in the United Kingdom?
(JCT) Joint Contracts Tribunal
(ACA) Association of Consultant Architects
(ICE) Institution of Civil Engineers
(NEC) New Engineering Contract
Stradia Ltd
List some of the commonly used standard forms?
- JCT Suite of contracts
- Association of Consultant Architects forms (ACA)
- General Conditions of Government Contracts for Building and Civil Engineering suite (GC/Works/1 Edition 3 19998)
- International Federation of Consulting Engineer (FIDIC)
- Institution of Chemical Engineers suite (IChemE)
- Public Sector Partnering Contract (PSPC)
Explain which situation the JCT Standard Building Contract with quantities is most suitable?
Architect or professional consultant.
Drawings and full bill of quantities
Project value over £1 million
Private or Public Sector.
Local authorities are encouraged to use NEC contracts.
Explain the situation when JCT Standard Form with approximate quantities is most suitable?
Drawings and approximate bill of quantities.
Usually over £1 million
Where the works cannot be accurately measured or where an early start is required.
Architect or professional consultant.
Explain the situation when JCT Standard Form without quantities is most suitable?
Usually up to £500,000.
Drawings, specification or schedules.
Not recommended if works are of a complex nature, that would be best tendered by a bill of quantities.
Architect or professional consultant.
Explain the situation when JCT Intermediate Form Contract is most suitable?
Value £100,000 to £10 million
Drawings and specification, schedules or a full bill of quantities.
For simple contracts not exceeding 12 months with limited specialist subcontractors.
Architect or professional consultant.
Explain the situation when JCT Minor Works Form Contract is most suitable?
Drawings and specification or schedules.
Up to £100,000
Simple contracts, short duration and few domestic subcontractors.
Architect or professional consultant.
Explain the situation when JCT Construction Management Contract is most suitable?
Drawings and specification or schedules.
Over £1 million
Complex projects requiring management expertise. Where an early start is required or accelerated work.
Architect or professional consultant.
Explain the situation when JCT Management Building Form Contract is most suitable? (4)
Drawings, specification or schedules.
Over £1 million.
Complex projects requiring management expertise. Where early start is required or accelerated works are required.
Architect or professional consultant.
Explain the situation when JCT Major Project Form Contract is most suitable?
Contractor lead designer.
Drawings and specification or schedules.
Value £100,000 to £100 million.
Where employer wants little or nothing to do with the project.
Explain the situation when JCT Design and Build Form Contract is most suitable?
Contractor is designer of the works.
Any value.
Employer’s requirements, contractor proposals and contract sum analysis.
Where the client requires no or few variations.
The project can be specified completely at the tendering stage.
CPD AND JCT Standard Building Contract with Quants.
Part architect and part contractor.
Drawings plus employers requirements for CPD.
Plus bill of quantities for client designed works.
Value £100,000 to £100 million.
Where some parts of the works are to be designed by the contractor.
JCT Intermediate with CPD.
Part architecture and part contractor.
Value £100,000 to £100 million.
Where some parts of the works are to be designed by the contractor plus schedules or bill of quantities.
JCT Measured Term Contract.
Maintenance work
Contract documents are Work orders
Generally used for periodic repair and maintenance.
JCT Repair and Maintenance Contracts.
Maintenance works
Contract documents basis is work orders.
Repair and maintenance contract.