Topic 2 - Project Cost Estimating Flashcards

1
Q

When do we do cost estimating?

A

Concept - estimate
Design - estimate
Bidding - estimate
Construction - estimate

Less effort/ low accuracy —-> more effort, more accuracy

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Why do we do cost estimating?

A

Financing and budgeting for owner and contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a conceptual estimate?

2 types?

A
  • completed prior to design
  • used by owner to determine feasibility of project and magnitude of scope(whether to proceed with project or not)
  • low accuracy
  • low effort
  1. Analogous estimating: “top-down” estimate based on previous projects: Cost per function, unit area, or unit volume methods
  2. Parametric estimating: statistical relationship between historical data and project variables/characteristics
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a preliminary estimate?

A
  • complated at +/- 40% of design stage
  • used to determine if company should proceed with project or not
  • can be used to evaluate alternate options
  • based on unit costs of similar cost elements from previous projects
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is an engineers estimate? aka owners estimate

A
  • COMPLETED AFTER DETAILED DESIGN IS FINISHED
  • used to conduct a final feasibility check
  • used to provide a reliable reference point for bids
  • can be used to secure resources (financing_
  • based on a detailed costing of each element of work in work breakdown structure (WBS)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a bid estimate/detailed estimate? -aka contractors estimate

A
  • most accurate
  • based on complete bid documents
  • “bottom up” estimating: detailed, first principles, based on lowest elements in WBS; includes detailed assessment of risks and opportunities and desired profit margin/markup
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Conceptual Estimate types?

A
  1. Analogous estimating: “top-down” estimate based on previous projects: Cost per function, unit area, or unit volume methods
  2. Parametric estimating: statistical relationship between historical data and project variables/characteristics
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Bid estimate/detailed estimate type?

A

-“bottom up” estimating: detailed, first principles, based on lowest elements in WBS; includes detailed assessment of risks and opportunities and desired profit margin/markup

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Classes of estimates

A

Class 1 to class 5

  • class 5 has very little maturity level (% of project completed), so will be most unnacurate and low preparation effort
  • class 1 has high maturity level (65%to100%), so has very high accuracy and high preparation effort
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Estimate class for bid/tender?

Estimate for feasibility?

Estimate for budget budget authorization/control?

A
  • class 4 or 5
  • class 1 or 2
  • class 3
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Methodology for class 4/5 estimates?

Methodology with class 3

Methodology with class 1/2

A

4/5: detailed unit cost with forced detailed take-off

3: semi detailed unit costs
1: capacity factored
2: equipment factored

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Competitive bidding/tendering: who is it conducted by?What is a tender? purpose of competitive bidding?

A
  • conducted by client (owner) or its consultant
  • a tender is a bid, a formal offer to do work based upon certain terms
  • purpose is to provide competition and thereby reduce costs to owners
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

5 methods of bidding?

A

-open competitive
-prequalified
-invited
negotiated
-joint ventures - one time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Steps in competitive bidding?

A

1) owner issues request for bids (letter of invitation, advertisement, request for pre-qualification, …)
2) contractor views/obtains tender documents
3) contractor makes decision to bod or not to bid
4) Contractor prepares estimate and tender submission
5) contractor submits bid

6) owner opens bids and awards contract
- public bid opening and closed bid opening

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Types of bid openings?

A

Public bid opening:

  • public sector owners (government, schools, hospitals)
  • basis for award: generally lowest price of prequalified

Closed bid opening:

  • private sector (non govt owners)
  • basis for award: not necessarily lowest price (experience, capability, realistic bid, quality of subcontractors and suppliers)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Additional elements of bid:

1) alternate price
2) separate price
3) breakout price

A

1) price for scaled up version of an item that is also priced in regular bid
2) price for a separate part of project that may or may not go ahead, depending on owners budget
3) indicate price for a specified portion of the work - used for accounting purposes to allocate funding

17
Q

Components of a detailed cost estimate

A
  1. Direct costs
    - labour, equipment, materials, subcontracts
  2. Indirect costs (overheads, preliminaries)
    - management, engineering, supervision
  3. Risk and opportunity allowance
  4. Margin / Markup
    - includes corporate overheads and profit
18
Q

steps in bidding process

A
  1. identify bid opportunity
  2. make decision to bid
  3. study plans and specifications
  4. break project into work packages (WBS)
  5. do quantity takeoff
    - of each work package, record quantity and unit of measure
  6. determine construction methods
  7. estimate labour and equipment productivity
  8. obtain and evaluate quotations from subcontractors and suppliers
  9. price items of work in WBS
  10. prepare project schedule
  11. price indirect (overhead) costs
  12. consider alternatives
  13. perform risk/opportunity analysis
  14. add corporate overhead and profit margin
  15. spread costs
  16. calculate unit prices
  17. submit bid
19
Q

How do we measure productivity?

A

Productivity = Output (units of products) / Input (resources)

Labour productivity = Output (installed quantity) / person-hours
(ex: output/input = 2m^3/person-hour)

Productivity refers to how efficiently and effectively a company can turn its input (labour and capital) into products and services

20
Q

Definition or production? How to change production rate?

A

=units of output per unit time (e.g 100m^3/hour for placing concrete)

-by changing number of person-hours available in one hour by changing crew size (increasing # of people) or by improving productivity

Production = Productivity (m^3/person-hour) * (person-hours/hour)

21
Q

Productivity vs Production

A

production indicates how much work is being done in a given time interval; how fast work is progressing; indicates if schedule objectives will be met; not an indication of how much money is being spent
-productivity is a measure of efficiency of labour and/or equipment crew; indicates if cost objectives will be met

22
Q

Capital Recovery Equation

Sinking Funds Equation

A

A = P[i(1+i)^n / (1+i)^n - 1]

  • A=gives the equivalent annual value (A) of the purchase price (P) assuming annual interest rate (i) during the useful life of (n)
  • i=MARR (minimum attractive rate of return) = interest for borrowing money + risk + average cost for taxes, insurance, storage

A = F[i / (1+i)^n -1]

  • F=future salvage value
  • i=annual interest rate
  • n=useful life, in years
23
Q

Estimating vs Bidding/Tendering

A

Estimating: Assessing direct costs and indirect costs

Bidding/tendering: assessing risk and opportunity allowance and margin

24
Q

What is risk and opportunity assessment

A

identifying and assessing the impact on costs of a potential project risks and opportunities

25
Q

What is a contingency (AACE)

A
  • contingency is an amount added to an estimate to allow for items, conditions, or events for which the state, occurrence, or effect is uncertain and that experience shows will likely result in additional costs
  • included in the estimate and expected to be expended (but not sure where)
  • accounts for stuff like uncertainty in productivity, unit rates, minor rice fluctuations, planning/estimating errors, design developments/change within scope
26
Q

What is risk and what is Risk allowance (AACE)

A

Risk is the degree of which dispersion or variability around the expected or “Best” value, which is estimated to exist for the economic variable in question

Risk allowance: may or may not be spend (based on probability of undesirable outcome), expected value of risk allowance will be spent, if correctly estimated

27
Q

Expected cost of risk? what are risk allowance and contingency? how much do we usually pay?

A
  • risk allowance and contingency are amounts of money used to provide for project risks, uncertainties, and unforseen costs that are associated with a construction project
  • a reasonable value (combination of risk allowance and contingency) should be included in the bid to cover for the risks involved in construction
  • 5% to 10% of contract price usually
28
Q

Risk and opportunity assessment: the math behind it?

A
  • identify items in the project which may have potential cost overruns (risks) or cost savings (opportunities)
  • assess the most likely $ cost or savings associated with each item
  • assess the probability of each cost or savings occurrence
  • multiply the $ cost or savings by its probability of occurrence
  • sum the total resultant costs and the total resultant savings: the difference between the two is the net project risk/opportunity allowance (contingency) (MAY BE + or -)
29
Q

Items covered by markup:

A
  • corporate overheads
  • profit
  • sometimes risk and opportunity allowance
30
Q

What does Break even analysis acomplish?

A

-to determine minimum (base) markup
OR
-to determine minimum volume of work (turnover) for firm to break even (i.e to cover corporate overhead costs, without making any profit)

31
Q

Break even analysis methods

A

Method A: predict turnover level ($) for coming year and calculate minimum markup (%)

Method B: Determine gross markup (%) (i.e profit + corporate overheads) on projects in coming year and calc minimum volume of work (turnover) ($)

32
Q

Steps in break even analysis (both methods)

A

Forecast corporate overheads for coming year:
-ex: previous yr: $200,000
-10% inflation $20,000
-firm growth: $30,000
Forecaster corporate overheads = $240,000

Method A: forcast turnover level (e.g $2,000,000)
-minimum markup: corporate overheads / Turnover
240,000/2,000,000 = 12%

Method B: forecast gross markup, e.g 12%

  • use break even analysis equations
    1) Revenue - Project Costs = Gross Profit
    2) Gross Profit - Corporate Overheads = Net Profit
    3) Gross Profit / Revenue = Gross Markup
  • at break even point, Net profix = 0, so;

From (2): Gross Profit = corporate overheads

From (1): Revenue = Project costs + Corporate Overheads

from (3):
Corporate overheads / Revenue = Gorss Markup

Revenue = Corporate Overheads/Gross Markup

In our example:
Revenue = 240,000/0/12 = 2,000,000

33
Q

What is a corporate overhead?

A

Corporate overhead refers to the indirect costs associated with running a business. In other words, corporate overhead encompasses all the costs that are not directly factored into producing a product or service. Common examples include administrative and marketing expenses.

34
Q

Methods of setting markup

A
  • BASED ON MINIMUM OR BASE MARGIN - BREAK EVEN ANALYSIS
  • based on resource cost category breakdown (to reflect risks inherent in each)
  • based on experience and market conditions
35
Q

Provisional and Prime cost items: What do we use them for?

Provisional quantities: name the 2 and describe them

A

We use provisional and prime cost items to calculate markup (margin), but spread markup to all items EXCEPT provisional and prime cost items

provisional quantities: -work which may not occur or variations in quantitiy expected
-safer NOT to allocate overhead or contingency spread to these items b/c they may or may not occur

prime cost items

  • owner stipulated sum of money, adopted by all bidders, for work not yet fully detailed
  • amount specified can not be modified by bidders
36
Q

Where do we spread overhead (indirect costs) and contingency to?

A

all items EXCEPT provisional and prime cost items.

37
Q

Strategic spreading? 2 Uses of strategic spreading?

A

for unit price contracts (paid on basis of actual quantities installed):

increase unit prices of items that are underestimated by owner

decrease unit prices of items that are over estimated by owner

-can be used to reduce overall bill price to be more competitive, or to increase profit margin while maintaining original bid price